Temporary Works

Who wrote the Report that set the standard for temporary works design and management in the UK? First name and title please.
Professor Stephen Bragg
 
 
How many principal recommendations was published in this report?
27
 
Please insert the missing words; Need for designer to consider minimum value of horizontal load (......% of vertical load + ........... Horizontal load or ........% of vertical load, whichever greater) (BS 5975 uses 2.5%)
1
Calculated
3
First published in 1982, what sets the basis of our company temporary works procedures?
BS5975
 
What is the Definition of Temporary Works?
€Works undertaken during construction to enable the permanent works to be constructed, or to stabilise or protect an existing structure, but that are not required to form part of the finally completed construction works.”
 
How many Temporary Works are in opration in this picture?
?
 
Create a question?
 
 
Create a question?
?
 
How many forms are there in the Temporary Works Design and Installation?
19
 
Where are copies of the procedure and forms stored?
Workspace
 
Name 3 things that are covered by Q25
Appointment of TWC / TWS
Identification of need for temporary works
Management of sub-contractors
Defining the problem
Design of temporary works
Checking of design
Insert the missing words; Design, .......... And removal of temporary works must be ........– Q25
Installation
Controlled
Every site must have a ..............
TWC
 
Site may have one or more ......... too
TWSs
 
......... Must be completed before temporary works ........ Or loading .......
Permit
Loaded
Changed
Permit must be completed .......... Temporary works removed
Before
 
Alterations to temporary works ......... Be approved in .........
Must
Advance
Name 2 Key Functions of a TWC
Ensure procedure followed
Identify need for temporary works
Produce briefs for and liaise with designers
Review designs to ensure meet site requirements
Why is it important that procedures are followed?
To reduce the risk of accidents.
 
{"name":"Temporary Works", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Who wrote the Report that set the standard for temporary works design and management in the UK? First name and title please., How many principal recommendations was published in this report?, Please insert the missing words; Need for designer to consider minimum value of horizontal load (......% of vertical load + ........... horizontal load or ........% of vertical load, whichever greater) (BS 5975 uses 2.5%)","img":"https://cdn.poll-maker.com/6-335953/temp-works.jpg?sz=1200-000000100053"}
Powered by: Quiz Maker