Lockout/Tagout Procedure Test - 20 Questions
What shift are you on?
What department are you in?
1. Only authorized associates are allowed to lockout equipment and machinery.
True
False
2. A press that is locked out does not need to have the ram blocked
True
False
3. If three people are working on the same piece of equipment, only one person has to put his or her lock on any switches, valves, or other energy isolating devices.
True
False
4. Auxiliary equipment (coil or sheet feeds, conveyors, etc.) attached to presses and other machines may need to be locked out while servicing or repairing the machine it is used with.
True
False
5. It's OK to work on a machine while its flywheel is still spinning
True
False
6. A machine must be locked out if safeguarding is removed or bypassed when servicing.
True
False
7. If a associate repairs a machine, but forgets to remove his or her lock before going home, only a supervisor can remove the lock.
True
False
8. It's not important to notify affected co-workers before you lockout equipment.
True
False
9. You should make sure all tools are removed and machine components are ready for operation before taking off locks and starting a machine that has been repaired.
True
False
10. Most machines have more than one source of hazardous energy that will need to be controlled by locking out, blocking, or dissipating.
True
False
11. Authorized associates can protect themselves while working on cord and plug connected equipment by placing a lockable cover over the plug or keeping the plug within arm's reach and in view.
True
False
12. Springs can cause sudden movement while repairing equipment, and should be blocked or otherwise made safe.
True
False
13. Before working on equipment, its operating controls should be operated after it is locked out to make sure the machine is safe.
True
False
14. Routine, repetitive, machine servicing takes place with safeguarding in place requiring the use of lockout procedures.
True
False
15. If working with an outside contractor, you should be aware of how he (or she) will lock out equipment, and make sure you are protected by lockout.
True
False
16. Turning off the power switch removes all energy from powered equipment and achieves a "zero energy state".
True
False
17. When you're finishing testing equipment to verify that it has been isolated from its energy sources, you must be sure to shut off all machine controls.
True
False
18. Applying locks or tags in the right places de energizes the equipment.
True
False
19. If a shift change takes place during lockout/tagout procedures, then the person leaving the job site will...
Keep their lock attacked and leave.
:eave the key to their lock in place where the arriving associate will find it.
Wait until the arriving associate locks out before removing their lock.
20. When should affected associates be notified that maintenance and servicing is done and the system is to be re-energized?
After locks and tags are removed, and before the system is re-energized.
You don't need to notify affected associates.
After work is done, but before locks are removed.
{"name":"Lockout\/Tagout Procedure Test - 20 Questions", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Associate Full Name:, Date of Test:, What shift are you on?","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}