In accordance with the requirements of Geotechnical investigation, what is the minimum number of boring shall be provided for piers or abutments over 30m wide?
1
2
3
4
For school buildings, all slab reinforcements shall be ____ minimum for bottom and top slab
20mm
25mm
30mm
40mm
For school buildings, camber all beams and girder atleast 6mm every ___ span, except cantilevers for which the camber shall be as noted in the plans but no case less than 20mm for every ____ span
2.5m, 3.0m
3.5m, 3.0m
4.5m, 3.0m
5.5m, 3.0m
For school buildings, all embedded pipes for utilities etc. That pass thru beams shall not exceed ____ in diameter or 1/3 beam depth width whichever is less
100mm
150mm
120mm
250mm
What is the maximum free height of the PVC sheet pile for revetments to limit potential deflection
1m
2m
3m
4m
What method is usually adopted when there is no visible evidence of termite infestation during soil poisoning?
Drenching
Waterlogging
Dousing
Cordoning
What method is usually adopted when there is visible evidence of termite infestation during soil poisoning?
Drenching
Waterlogging
Dousing
Cordoning
For pre-painted metal sheets what is the minimum end laps that shall be provided?
100mm
150mm
120mm
250mm
Warranty period for permanent structures as per RA 9184
10y
15y
20y
25y
What is the minimum headroom between the pedestrian walking surface and bottom of girder of the structure like railway, flyover and bridge above shall be ____
1m
2m
3m
4m
What is the minimum vertical clearance above road carriageway for flyovers, bridges and railways?
5.33m
4.88m
5.3m
5.03m
What is the minimum vertical clearance above road carriageway for pedestrian footbridges?
5.33m
4.88m
5.3m
5.03m
Advance payment to the contractor in an amount not to exceed ___ of the total original contract amount
10%
20%
15%
5%
Withholding VAT for progress billing of the contractor shall be?
3%
2%
10%
5%
Total amount of liquidated damages shall be deducted to the _____
Retention
Bond
Interim billing
Final billing
It reflects accomplishment-duration relationship in the project
Catch up schedule
S curve
Time slippage
Gantt chart
It is the graphical representation of the cumulative monthly cash flow of a project over its time duration
Catch up schedule
S curve
Time slippage
Gantt chart
Contract time extension may be granted only when the affected activities fall within the ____ of the PERT/CPM or PDM network
Lag time
Lead time
Critical path
Free float
It is the difference between the targeted accomplishment and the actual accomplishment at the end of a certain period, it is expressed in percentage and indicates the performance of project implementation
Catch up schedule
S curve
Time slippage
Gantt chart
One eligibility requirement for contractors is to be a Filipino Citizen or at least ____ Filipino owned partnership or corporation
50%
60%
75%
80%
What is the design life span of permanent bridges before it is being replaced?
50y
60y
75y
25y
What do you call the clearance between the design flood level (DFL) or the maximum experienced flood level (MEFL) and the (soffit) of the lowest member of the bridge superstructure?
Bridge length
Span length
Abutment
Freeboard
This is very suitable for shallow foundation and for areas wherein the hard strata lie 3m below the NGL for firm materials and 5m below the NGL for soft materials
Spread footing
Caisson
Pile foundation
Bored
This is equal to the tip elevation minus the "cut-off elevation" or bottom elevation of the pile cap.
Casting length
Standard length
Furnished length
Driven length
What is the maximum allowed span length for reinforced concrete deck girder?
20m
24m
25m
30m
What is the suggested type of pre-stressed girder to be used when the span length is 35m?
Type VII
Type VI
Type V
Type IV
What is the suggested type of pre-stressed girder to be used when the span length is 18m?
Type III
Type II
Type VI
Type IV
What is the maximum jacking force for pre-stressed girders?
85%
75%
60%
80%
MEFL means Maximum ____ Flood Level
Encountered
Experienced
Evaluated
Elevation
Dike height = free board + ____
DFL
MEFL
OFL
OWL
Generally, what is the minimum freeboard allowance above the MEFL and DFL Revetments?
0.5m
0.6m
1m
1.5m
Minimum overall thickness should be ___ for all types of revetment, except for reinforced concrete type.
250mm
200mm
300mm
100mm
What is the maximum span length of spur dike?
250m
200m
300m
100m
Groundsill are structures constructed ____ to the flow of the river
Perpendicular
Against
Asymptotic
Parallel
For creeks in urban and rural areas and not subject to overbank flows, a minimum easement to be provided measured from the edge of the existing bank or the improved bank should be ____
2.5m
4.5m
5.5m
3.5m
River, esteros and navigating canals, not subject to overbank flows should have a minimum easement measured from the edge of the existing bank or the improved bank of ____
5.2m
5.3m
5.4m
5.5m
This is where the computation of contract price escalation of a project that is awarded thru "public bidding" should be based and reckoned.
Date of bidding
Approval of the contract
Notice to proceed
Notice of award
This is where the computation of contract price escalation of a project that is awarded thru "simplified bidding" should be based and reckoned.
Date of bidding
Approval of the contract
Notice to proceed
Notice of award
In horizontal alignment of roads and highways, what is the maximum algebraic difference of cross-over?
6%
7%
8%
9%
For roads and highways, what is the minimum recommended width of curve widening?
0.6m
0.7m
0.8m
1m
What is the validity / renewal period of the PE accreditation?
2y
1y
5y
3y
The spacing of the bars at the column strips for school building shall not be more than ____ slab thickness
1 1/2
2 1/2
1/2
1 1/3
Statement: No pipes shall be embedded in columns of the school building
False
True
Maybe
Maybe, provided that the ductile Point does not exceed L/3 of the clear height
Statement: No pipes shall be allowed to pass thru beams of the school building vertically
False
True
Maybe
Maybe, provided that the ductile Point does not exceed L/3 of the clear span
Statement: Splicing of PVC sheet piles for revetments shall be allowed
False
Maybe, provided that the weepholes are spaced 2m vertically and horizontally
True
For combination of bored/steel sheet pile for bank protection, what is the minimum N-value capable developing the required ultimate bearing capacity?
10
15
20
None of the above
What is the minimum end laps for corrugated metal roofing?
100mm
150mm
250mm
None of the above
As per RA 9184, rule IX what is the warranty period for semi-permanent structures or building types 1, 2, and 3
10y
15y
3y
None of the above
What is the durometer hardness for elastomeric bearing pads which is 100% virgin chloroprene (neoprene) pads?
40
50
60
75
In rural areas, what is minimum bridge pedestrian width
1000mm
500mm
1200mm
750mm
In urban areas, what is minimum bridge pedestrian width?
1000mm
500mm
1200mm
750mm
What is the maximum height of bridge abutment
10m
15m
20m
25m
For service load design of bridges, what is the flexural stress in the extreme fiber stress in compression?
0.2fc'
0.3fc'
04fc'
0.5fc'
For effective drainage, the slope of edge of pavement shall be less than or equal to ___ between +-1.5% grade
0.4%
0.3%
0.25%
0.5%
What is the cross slope of the higher shoulder for roads and highways when the super elevation is 4%?
-4%
-3%
-2%
-1%
What is the cross slope of the higher shoulder for roads and highways when the super elevation is 5%?
-4%
-3%
-2%
-1%
What is the minimum depth of roadside channel from the bottom of pavement?
500mm
600mm
750mm
1000mm
What is the minimum width of PCCP on National Highways per lane?
3.25m
2m
3.35m
2.8m
What is the minimum width of PCCP on farm to market roads per lane?
3.25m
2.8m
3.35m
2.5m
What is the minimum length of the radius of horizontal curve for PCCP on farm to market Roads?
15m
20m
25m
30m
What is the minimum diameter size of pipe culverts?
950mm
925mm
910mm
900mm
In an emergenct, the head of the procuring entity may authorize a Variation order beyond 10% but not more than ____ of the original contract price following the guidelines determined by Government Procurement Policy Board (GPPB)
10%
20%
15%
5%
Processing of advance payment shall require that minimum of ____ of the scope of work should be workable or free from obstruction
30%
20%
15%
10%
Early warning stage happens when the negative slippage of the project accomplishment is ___?
10%
20%
15%
5%
ICU stage happens when the negative slippage of the project accomplishment is ___?
10%
20%
15%
5%
Terminal Stage happens when the negative slippage of the project accomplishment is ___?
10%
20%
15%
5%
During bidding, the bidder may sub-contract a material or significant portion of the goods which must not exceed ____ of the contract price
10%
20%
15%
5%
The BAC shall determine to its satisfaction where the bidder that is evaluated as having submitted the ____ complies with and is responsive to all requirements and conditions
Highest calculated bid
Lowest calculated bid
Lowest computed bid
Highest computed bid
What do you call the overlap between the first and second activity in PERT CPM/PDM
Lead time
Lag time
Free float
Lapping
It is measured from back of backwall to back of backwall of the bridge
Bridge length
Span length
Pile length
Freeboard
It is a temporary wall installed to exclude water to allow construction work within the are protected by the _____.
Pier
Cofferdam
Abutment
Wingwall
It provides access for equipment to the location of the foundation of the bridge.
Pier
Cofferdamn
Craneway
Wing wall
There are rectangular piles which can take huge axial loads and high moments, ideal for boulder ground and alluvial soil but adaptable to most type of ground
Bored piles
Barrette piles
Pre-stressed piles
Timber piles
The main objective of the ____ dynamic test is to determine pile bearing capacity
High strain
Low strain
Medium strain
Strain
Statement: pouring permit for PCCP is the same from pouring permit on bridge structures.
False
True
Maybe
Maybe, if the volume does not exceed 1500m3
When borehole drilling using super mud, what is the pH range of pre-treat water with soda ash?
4.5-8
6.5-8
8-10
8-10.5
What is the minimum head pressure required to drill when borehole drilling using super mud?
1.25m
1.5m
1.4m
1.2m
When concreting of bored piles, overpouring in the quantity of ___ of the theoretical volume is considered "in order"
15-20%
10-12%
10-15%
10-20%
What is the diameter of the High tensile strand used in pre-stressed concrete girders?
12.7mm
12.6mm
11.7mm
11.6mm
What do you call the bridge with superstructure perpendicular to its substructure?
Normal
Skewed
Curved
Standard
What do you call the bridge with superstructure NOT perpendicular to its substructure?
Normal
Skewed
Curved
Standard
A change order may be issued when the aggregate cost is limited to ____ of the original contract cost,
30%
20%
25%
10%
What is used to emphasize to the approaching driver a marked change in the direction of travel and the presence of an obstruction
Hazard Markers Type HH
Hazard Markers Type HN
Hazard Markers Type MM
Hazard Markers Type HHHM
On simple curves, widening of curves should be applied on the edge only.
Inner
Outer
Niddle
1/3
The revision length of tangent between reversed curve should be 50mm and in no case, should be less than ____.
25m
30m
40m
20m
Gradients/grades of roads, highway and bridges should be as ___ as possible
High
Flat
Moderate
Curve
Vertical alignment of roads shall require that for every degree of curvature six degrees, the ruling grade shall be reduced by ____
0.3%
0.2%
0.25%
0.1%
Which of the following is not a classification of a terrain?
Level
Rolling
Volcanic
Mountainous
What is the vertical alignment scale for the road plan preparation?
1:100
1:500
1:1000
1:10000
What is the horizontal alignment scale for the road plan preparation?
1:100
1:500
1:1000
1:10000
What is the minimum preferred slope on pipe culverts?
0.3%
0.2%
0.25%
0.1%
Pipe culverts shall be laid at such grades that there will be a cushion of at least ___ of fill over the top of the pipe.
0.3m
0.4m
0.5m
0.6m
What is the maximum allowable grade for national roads?
10%
6%
7%
8%
What is the length of the road widening from center of the road left and right side for national roads?
20m
15m
7.5m
6m
What is the length of the road widening from center of the road left and right side for municipal roads?
5m
15m
7.5m
6m
What is the length of the road widening from center of the road left and right side for barangay roads
5m
15m
7.5m
6m
What is the minimum travelled way for provincial roads?
6.1m
4m
6,7m
6.6m
What is the minimum road right of way (RROW) for national roads?
20m
15m
7.5m
6m
What is the minimum road right of way (RROW) for municipal roads?
20m
15m
7.5m
6m
What do you call the depth of water above the culvert inlet bottom?
Headwater
Outflow
Inflow
Scoured
What do you call the depth refers to the total depth of water from surface to a purged bed level?
Headwater
Outflow
Inflow
Scoured
What is the range of Spur dike's top width?
1-2m
2-3m
3-4m
1-3m
For concave sections, why is the distance between spur dikes times the length of spur?
1.4x1.8xLS
1.7 to 2.3 x LS
2.8 to 3.6 x LS
All the above
For convex sections, what is the distance between spurdikes times the length of spur (LS)
1.4 x 1.8 x LS
1.7 to 2.3 x LS
2.8 to 3.6 x LS
All the above
What is the minimum Radius of curve for a design speed of 30kph?
20m
15m
30m
25m
What is the minimum bandwidth of the reflective tapes for traffic cones?
200mm
150mm
300mm
250mm
What is the standard maximum height for traffic bollards?
2m
1.5m
1m
2.5m
Concrete barrier need to be continuous to be continuous or secured together, generally using steel pins and eyelets, with a maximum ___ gap to ensure they perform satisfactorilly
600mm
500mm
400mm
750mm
What is the standard distance range of road warning signs in advance of the construction site for urban areas?
30-100m
25-50m
75-225m
100-200m
What is the standard distance range of road warning signs in advance of the construction site for rural areas?
30-100m
25-50m
75-225m
100-200m
Barrier boards shall not be used for delineation purposes or installed parallel to vehicular traffic unless there is an offset of atleast ___ from the travelled path
1m
2m
3m
4m
Traffic cones shall be spaced ___ apart on tapers and around small work sites.
5-10m
6-10m
4-8m
5-8m
What kind of reports are used to document events that occur at a plant or operation, such as concrete batch plant or bituminous plant?
Contract performance reports
General project reports
Field correction reports
Plant inspector's report
These are monthly or quarterly statements of time and cost for the project. The report documents all changes that have accrued since the beginning of the project regarding time and cost
Contract performance reports
General project status reports
Field correction reports
Plant inspector's report
What kind of report are used to summarize the work progress for the immediate preceding month or quarter. Usually contains a narrative section describing status of project, s-curve diagram summary of contract time and change orders?
Contract performance reports
General project status reports
Field correction reports
Plant inspector's report
What kind of report are used to document any corrective changes which occur in the field that would require departure from the plans and specifications and then provide the necessary information to understand the problem, decide of how to resolve it and issue instructions to the field and serve as a source of document for variation order approvals?
Contract performance reports
General project status reports
Field correction reports
Plant inspector's report
After the issuance of the punch list during the pre final-inspection, ____ months-time duration imposed to complete the project without penalties.
1
2
3
4
This represents the payment of the remaining balance of the contract including the total retention after the completion of the project
Final billing
Interim billing
Retention billing
Pre-final billing
The contractor will be allowed to file for the release of first partial billing if he had satisfactorily completed atleast ____ of the contract amount
10%
30%
20%
25%
When the spread footing location on a slope, the minimum distance from the lower edge of the footing to the sloping ground surface should be ____
500mm
1000mm
750mm
900mm
What is the maximum spacing center to center of adjacent rings of circumferential reinforcement in a cage of standard two-meter RCPC?
100mm
50mm
75mm
90mm
For school buildings, footing shall rest atleast ____ below natural grade line.
1m
1.5m
2.5mm
2mm
For buildings, the minimum concrete protection for reinforcement shall be ____ clear for concrete deposited the ground.
100mm
50mm
75mm
90mm
For buildings, the minimum concrete protection for reinforcement shall be ____ clear for concrete deposited a formwork.
100mm
50mm
75mm
90mm
What is the minimum days of stripping of forms and shores for suspended slab in school building?
1day
8days
14days
21days
What is the minimum days of stripping of forms and shores for walls and columns in school building?
1day
8days
14days
21days
This is the guidelines on the accreditation of the contractors and consultant's project engineer
DO 10 s 2019
DO 15 s 2019
DO 30 s 2019
DO 20 s 2019
What is the minimum girder required for a one lane bridge?
6
3
4
5
What is the minimum girder required for a 2-lane bridge?
6
3
4
5
Construction joints in floors hall be located within the ____ of spans of slabs, beams, and girders. Joints in girders shall be offset a minimum distance of two times the width of intersecting beam.
L/3
L/4
Middle thirds
L/2
All embedded pipes for utilities etc. That pass thru beams shall not exceed 100mm in diameter or beam depth whichever is less, and no pipes shall be allowed to pass thru beams vertically.
1/3
1/4
3/4
1/2
The ACI code gave a provision on structural integrity to perimeter beams is to splice continuous top bars at ___ and splice continuous bottom bars at or near supports
Middle thirds
Mid span
Top slab
L/4 from support
All doors for people with disability (PWD) shall have minimum clear width of ____ meter
0.80m
0.90m
1m
1.2m
All sidewalks/walkways for people with disability (PWD) shall have a minimum clear width of ___ meter
0.80m
0.90m
1m
1.2m
As per IRR 344, handrails attached to walls should have a clearance no less than ___ from the wall
80mm
90mm
50mm
75mm
All sidewalks / walkways for people with disability (PWD) shall have a maximum grade of?
4%
5%
6%
3%
No vertical curve is required when algebraic difference between grades is less that _____
0.4%
0.5%
0.6%
0.3%
What do you call the discharge used to size the capacity of the bridge?
Design flood
Flood level
MEFL
OWL
What is the maximum spacing of bridge drains?
3m
4m
6m
5m
What is the minimum diameter of bridge drains?
100mm
150mm
75mm
200mm
What is maximum design span for box girders?
15m
20m
25m
30m
What is the minimum design thickness for asphalt overlay projects?
25mm
50mm
75mm
100mm
What is the minimum STE individual years of experience for Class A Category AA Contractor
5y
10y
15y
12y
What is the maximum allowable single project cost for Small B Category C contractor?
15million
10million
25million
20million
What is the maximum allowable contract cost for medium A category B contractors?
150million
100million
250million
200million
What is the minimum width of turnouts, loading and unloading bay, to accommodate all types of vehicles
3.2m
3.5m
3.6m
3.75m
What is the standard color for all DPWH steel bridges?
Blue
Gray
Black
Orange
National Numbering system (NRS) should remain over the medium term and reviews shall be undertaken on a periodic ____ cycle.
5y
6y
7y
8y
What is the minimum width of Zebra (Longitudinal bars) for pedestrian crossing markings?
3m
3.5m
4m
5m
Pedestrian crossing markings at road intersection without channelization islands shall be placed outside the intersection area at least ____ set back from the edge of the road
2m
2.5m
3m
4m
Who is the approving official if the work suspension order is 85 calendar days?
DE
RD
Assistant Sec.
Undersecretary
What is the standard dimension for Project Billboard?
1.22mx2.44m
1.5mx2.5m
2.12mx2.14m
1.3mx2.44m
For road projects with length of 10 kilometers or more, additional billboard shall also be installed at every ____ interval.
3.0kM
4.50kM
5.0kM
7.5kM
No other billboards shall be allowed to be installed __ before and after all DPWH projects and in-between the project limits or within the road right-of-way.
100m
150m
30m
50m
It is acceptable for "A-Built Plans" as a reason for final variation order of the cumulative increase in value of work does not ___ of the adjusted original contract price.
5.0%
12.0%
10%
15%
What is the maximum amount for Regional Directors to approved Program of Work, ABC and plans like as-built and as-staked?
200 Million
50 Million
300 Million
100 Million
What is the maximum amount for "selected" District Engineer to approved Program of Work, ABC and plans as-built and as-staked?
200 Million
50 Million
300 Million
100 Million
What is the maximum amount for "ALL" District Engineer to approved Program of Works, ABC and plans as built and as-staked?
200 Million
50 Million
300 Million
100 Million
What is the minimum pavement thickness for Farm to Market Roads?
200 mm
250 mm
230 mm
280 mm
What is the minimum Radius of Horizontal Curve for Farm to Market Roads?
20 m
50 m
30 m
40 m
What is the minimum Radius of Horizontal Curve for Tourism Roads?
20 m
50 m
30 m
40 m
The RROW boundary marker posts shall be installed along the RROW limit line on each side of the road at __ kilometer interval.
1km
5km
3km
4km
On highly urbanized area, RROW marker shall be concrete block embedded on the surface along the edge of concrete sidewalk on each side of the road at ___ interval.
100 m
500 m
200 m
250 m
All permanent bridges along national roads shall be provided with the Informative signs to be posted on conspicuous place within ___ before the abutment at both approaches.
1 m
5 m
3 m
4 m
What is the negative slippage for "ICU Stage"?
5 %
10%
15%
20%
What is the negative slippage for "Terminal Stage"?
5%
10%
15%
20%
What is the maximum distance outside the shoulder for Kilometer Post from the edge of the road pavement?
1.5m
2.50m
1.0m
2.0m
If a shoulder is less than 2.0m, what is the setback distance of the Kilometer Post from the edge of the shoulder?
0.75m
0.50m
1.0m
2.0m
What is the spacing of dowels bars for 280 mm thick PCCP?
300mm
274mm
250mm
295mm
What is the spacing of dowels bars for 300 mm thick PCCP?
300mm
274mm
250mm
295mm
Vertical Clearance for Bridges over Navigable Waterways is the sum of Highest Water Level (HWL) and Height of Vessel (HV) and the K Factor. What is the constant value of the K-factor?
1.5m
2.50m
1.0m
2.0m
Contractor shall shoulder all the expenses for the alteration and/or reconstruction of the structure and a fine of ___ of the original total contract price, if they violated the minimum Vertical Clearance for Bridges over Navigable Waterways.
1.5%
2.50%
1.0%
2.0%
What is the setback distance from the RROW Limit for Welcome Arches and Overhead Boundary Markers?
1.5m
2.50m
1.0m
2.0m
For span lengths of 21-30 meters, what bridge type shall be use as per Department Order No. 30 Series of 2011?
Flat Slab
RCDG
PSCG
Steel Bridge
For span lengths of 6-12 meters, what bridge type shall be use as per Department Order No. 30 Series of 2011?
Flat Slab
RCDG
PSCG
Steel Bridge
Which pf the following contractor category is not required for ISO 9000 Certification?
Large B
Large A
Medium B
None OTA
What is the minimum individual years of construction experience for Sustaining Technical Employee (STE)
2 years
3 years
5 years
10 years
What is the minimum individual years of construction experience for Sustaining Technical Employee (STE) for all Classes and Categories of a Contractor?
2 years
3 years
5 years
10 years
What is the minimum Financial Capacity, Net Worth/Equity of a Class A Category A Contractor in Pesos?
20 Million
25 Million
30 Million
50 Million
What is the minimum Financial Capacity, Net Worth/Equity of a Class A Category AAAA Contractor in Pesos?
1 billion
750 Million
10 billion
500 Million
What do you call the project scheduling Technique used for DPWH Projects?
PDM
PERT
CPM
All of ABove
If the actual soil bearing capacity of the natural ground is less than 96 kPa at depth of 1.5m, what is the maximum depth of the isolated footing?
2.0m
2.5m
3.0m
5.0m
What is design Speed for Flat Terrain of Tourism Roads?
50kph
40kph
30kph
60kph
What is design Speed for mountainous terrain of Farm to Market Roads?
50kph
40kph
30kph
60kph
What is design Speed for Flat terrain of Farm to Market Roads?
50kph
40kph
30kph
60kph
What is the roadway cross slope for PCCP?
1.25%
1.50%
2.0%
3.0%
What is the roadway cross slope for gravel surfacing of sidewalk?
1.25%
1.50%
2.0%
3.0%
It is the physical island at the center of a divided roadway separating traffic flows.
Median Island
Middle Island
Channelizing Island
Channelized Island
It is designed to control and direct traffic movement, usually turning.
Median Island
Middle Island
Channelizing Island
Channelized Island
As a minimum requirement for Bridge projects __ bored pile(s) shall be tested representing each pile size.
1
2
5
4
For buildings, at least __ of the total number of bored piles shall be tested.
1%
2%
5%
4%
As per BP 344, Handrails attached to walls should have a clearance no less than 50mm from the wall and handrails on ledges should have a clearance not less than __.
100mm
20mm
50mm
40mm
What is the minimum raised height required for signages/symbols labeling public rooms and places?
1mm
2mm
5mm
4mm
To guide the blind, sidewalks should as much as possible follow straight forward routes with __ angle turns.
45 degree
135 degree
Right
Left
What is the minimum width of the refuge island and its total total length?
2.5m, 30m
1.5m, 30m
3.5m, 30m
2.0m, 30m
The Refuge island shall be provided in roadways having clear carriageway width of at least __ lanes.
2
4
6
8
What is the flood flow velocity criteria in designing slope protection works?
3m/sec
4m/sec
5m/sec
10m/sec
What is the minimum desirable length of Turnouts, unloading and loading bays, on national roads?
100mm
75mm
50mm
60mm
What is the maximum length of Turnouts, unloading and loading bays, on national roads?
150mm
175mm
185mm
200mm
If the actual soil bearing capacity of School Building did not meet the required 96 kPa soil bearing capacity, the implementing office may opt to perform/use the following except one:
Micro-piles
Mat Foundation
Bored PIles
H-Piles
What is the width of the Stop Line in Urban Roads?
500mm
750mm
450mm
600mm
What is the width of the Stop Line in Rural Roads?
500mm
750mm
450mm
600mm
When using Reclaimed Asphalt Pavement (RAP) as partial replacement to coarse aggregate in Hot-Mix Asphalt (HMA), what is the maximum % for Item 320 Grading D and Grading B?
35%, 65%
40%, 60%
25%, 40%
35%, 40%
If the actual condition of the soil in school building is susceptible to liquefaction , ground improvement technique may be performed except one;
Permeation Grouting
Jet Grouting
Compaction Grouting
None of the Above
The minimum Bridge Carriageway width for Tourism Roads.
6.70mm
7.50mm
5.60mm
6.10mm
The minimum Bridge Carriageway width for 5.0m width - Farm to Market Roads.
6.70mm
7.50mm
5.60mm
6.10mm
The minimum Bridge Carriageway width for 6.1m width - Farm to Market Roads.
6.70mm
7.50mm
5.60mm
6.10mm
What is the flood frequency used in hydraulic analysis for bridge design?
25 years
15 years
50 years
100 years
For Pre-Cast Concrete Curb and Gutter, minimum curb inlet interval (D) is __ in flooded areas and ___ in other areas.
10m, 20m
5m, 10m
25m, 50m
15m , 30m
For multi-span bridges, Pile Bearing Capacity Test shall be conducted ___ at each abutment and 1 at every other pier.
1
2
3
4
Pile Integrity Test shall be conducted on at least ___ of the total number of bored piles at each abutment and pier of bridges or at the entire foundation area of buildings.
10%
25%
50%
30%
Cross hole Sonic Logging Test (CSL) is recommended for bored piles with embedded length of more than ___.
10m
25m
50m
30m
What is the minimum width of a curb cut-out?
1.0m
0.80m
0.50m
0.90m
When the AADT is greater than ___ vehicles, paving of shoulder is necessary.
1,000
1,250
1,500
2,000
Minimum distance between two consecutive pedestrian refuge islands along the highway shall not be less than ___ meters.
100m
250m
500m
200m
What is the Navigational Clearance of a bridge over navigable waterways with the given data: HWL=15.0m and HV=10.0m
25m
26m
28m
30m
If the length and width of the drainage area is equal to 50m and 100m respectively; what should be the length of the channel?
136.8m
138.6m
125.8m
151.5m
Compute the amount of Liquidated Damages (LD) given the following data: Remaining scope of work amount is PHP 1,000,000.00 and the contractor completed the remaining scope of work in 15 calendar days time
15,000
20,000
10,000
25,000
Defects Liability Period
1year
2years
3years
5years
As per RA 11058, the General Contractor must provide one (1) Construction Safety and Health Officer for every ___ units of Heavy Equipment assigned to the project site to oversee the effective compliance with the COSH Program.
5 units
10 units
15 units
8 units
What is the maximum gradient for Curb Cut-Outs?
1:12
1:20
1:00
1:50
What is the maximum gradient for sidewalk as per BP 344?
1:12
1:20
1:100
1:50
As per BP 344 requirement, what is the walking speed design on the crossings?
1.0m/sec
1.20m/sec
0.90m/sec
1.10m/sec
What is the length of tangent between reverse curves for both tourism and farm to market roads?
60m
30m
40m
50m
For roadway obstructions, such as bridge piers, what is the width of the black and white stripes on the object marking?
100m
300m
250m
50m
For roadway obstructions, such as bridge piers, what is the minimum width of the black and white stripes on the object marking?
100m
300m
250m
500m
For raised median island, planting of trees should not be permitted on Highspeed multilane divided highway and the surface level of soil fill shall be lower than the top of island - 50mm for island height less than or equal to ___ and 10mm for island height greater than ___
0.45m
0.5m
0.35m
0.65m
The pavement thickness of turnout, unloading and loading bays, shall in no case be less than ___ for asphalt and 230mm for concrete with supporting base layers.
100m
300m
250m
50m
During road re-blocking works, holes of ___ diameter and spaced at 300mm shall be drilled at 1/2 of the existing concrete pavement thickness to permit the load transfer transverse construction joint.
260m
300m
250m
350m
The procuring entity shall, upon a written request of the contractor which shall be submitted as a contract document, make an advance payment to the contractor in an amount not exceeding blank percent of the total contract price?
5%
10%
20%
15%
The advance payment shall be repaid by the contractor by deducting fifteen percent from his payments on
Final billing
First progress billing
Periodic progress biliing
Quarterly billing
This is issued by the procuring entity to cover any increase/decrease in quantities, including the introduction of new work items that are not included in the original contract.
Variation order
Supplementary letter
Job order
Work request
May be issued by the implementing official to cover any increase/decrease in quantities of original work items in the contract.
Job order
Extra work order
Change order
Work instruction
May be issued by the implementing official to cover the introduction of new work necessary for the completion, improvement or protection of the project which was not included as items of work in the original contract.
Job order
Extra work order
Change order
Work instruction
An amount equal to one-tenth of one percent of the cost of the unperformed portion of the works for every day of delay.
Retention money
Liquidated damages
Security bond
Performance bond
Total sum of liquidated damages shall not exceed blank percent of the total contract price, in which event the procuring entity concerned may rescind the contract.
15%
10%
20%
5%
Is a written order issued to by DPWH Project Engineer to suspend the contract work wholly or partly for such period?
Change order
Variation order
Work suspension order
Contract time extension
Issued instead of Work Suspension Order if suspension / unworkable days is due to unfavorable weather condition (Rainy), weather disturbances or its effect (river swelling, storm surge, etc.), or other conditions rendering the site unworkable occur intermittently.
Change order
Monthly time suspension report
Work suspension order
Contract time extension
Is a written order issued by the DPWH Project Engineer to the contractor to resume construction operation covered by a previous Work Suspension Order, after the cause of or reason for the work suspension has been resolved.
Change order
Variation order
Suspension of work
Work resumption order
Is a written authority issued by DPWH Project Engineer granting the contractor additional time beyond the approved completion date in order to carry out remaining works or any additional works?
Change order
Variation order
Suspension of work
Contract time extension
Who is the delegated authority for local project authorized to issue Work Suspension Order, Work Resumption Order and Contract Time Extension, including the determination of the inclusive period necessary with cumulative inclusive period up to 60 days?
DE
RD
Cluster director
Undersecretary
Who is the delegated authority for local project authorized to issue Work Suspension Order, Work Resumption Order and Contract Time Extension, including the determination of the inclusive period necessary with cumulative inclusive period beyond 60 days?
DE
RD
UPMO cluster director/Bureau director/ Undersecretary
Usec. For tech serve/UPMO operations
Who is the delegated authority for central/ UPMO project authorized to issue Work Suspension Order, Work Resumption Order and Contract Time Extension, including the determination of the inclusive period necessary with cumulative inclusive period beyond 120 calendar days?
DE
RD
UPMO cluster director/Bureau director/ Undersecretary
Usec. For tech serve/UPMO operations
This is prepared once the project reaches an accomplishment of ninety five percent of the total contract amount in preparation for the final turnover of the project.
Certificate of completion
Punchlist
Project bonus
Certificate of acceptance
The Procuring Entity shall terminate for default a contract for goods if Supplier fails to deliver or perform at least how many percent of the contract price within the periods specified in the contract
10%
15%
20%
25%
Procuring Entity shall terminate for default a contract for Infrastructure Projects when any of the following conditions attend its implementation due to the Contractor’s fault and while the project is on-going, it has incurred negative slippage of how many percent or more in accordance with Presidential Decree 1870;
10%
15%
20%
25%
Procuring Entity shall terminate for default due to the Contractor’s fault and after the contract time has expired, it has incurred a negative slippage of blank percent or more.
10%
15%
20%
25%
What is the minimum average compressive strength for a non-load bearing Concrete Hollow Blocks (CHB)?
500psi
600psi
700psi
800psi
How many pieces of Concrete Hollow Blocks (CHB) per square meter are used in the Cost Estimation?
12.5
13
12.5 plus 5% wastage
None of the above
What is the cement sand ratio to achieve 500 psi Concrete Hollow Blocks?
1:2
1:3
1:5
1:6
What is the minimum corrugation overlap on roofing sheet installation?
2
2.5
3
3.5
What is the mix ratio by volume of the mortar used in the installation of CHB and Louver blocks?
1 part cement :1 part sand
1part cement : 2 part sand
1 part cement : 3 part sand
1 part cement : 4 part sand
What is the design standard width for tourism and farm to market road projects?
Minimum of 6.1m for two lanes
Minimum of 4.6m for two-lanes
Minimum of 5.6m for two-lanes
Minimum of 6.7m for two-lanes
How many project billboards are installed for each road/bridge/flood control project?
1
2
3
4
What is the dimension of a DPWH project billboard?
2x4 ft
3x6 ft
4x8 ft
8x16 ft
Is the total estimated cost of the project which covers the Civil Works Cost, Engineering Supervision and Administrative Overhead, Road Right-of-Way Acquisition Cost, Construction Contingency, etc. Include information about the project location and limits, quantity and unit cost for each item of work, construction duration, funding source, equipment requirements, etc.
Approved Budget for the Contract (ABC)
Detailed Unit Price Analysis (DUPA)
Program of Works (POW)
Commission
Is the total estimated agency estimate (direct cost, indirect cost and tax) for civil works contract of infrastructure projects, wherein it is the ceiling of award of contract for government locally-funded projects and reference for comparison of bid costs of contractors for both locally-funded and foreign-assisted projects.
Approved Budget for the Contract (ABC)
Detailed Unit Price Analysis (DUPA)
Program of Works (POW)
Commission
Is the determination of reasonable unit cost of each item of work which reflects the breakdown showing the quantities of work items, unit prices of materials, equipment rental rates, labor rates and DPWH-prescribed indirect costs including taxes?
Approved Budget for the Contract (ABC)
Detailed Unit Price Analysis (DUPA)
Program of Works (POW)
Commission
One-storey up to 5-storeys in height, I.e., from 3.00 m up to a maximum of 15.00 meters above established grade.
Low rise building
Midrise building
High rise building
Team building
How many percent is shrinkage factor used for material cost estimation of Embankment from Common Borrow by Equipment?
10%
15%
20%
25%
On the preparation of detailed unit price analysis, allowance for waste and/or losses shall not exceed _____ % of the material's requirement.
10%
8%
7%
5%
How many percent is shrinkage factor used for material cost estimation of Gravel Bedding?
5%
10%
15%
20%
What is the minimum cement content per m3 on a class A concrete?
9
9.1
9.5
8
What is the minimum cement content per m3 on a class C concrete
9
9.1
9.5
8
What is the minimum cement content per m3 on a Lean Concrete (for manual mixing)?
6
7
8
9
What is the unit weight of a 10mm diameter RSB?
0.628
0.617
0.820
0.817
What is the nominal weight of 16mm diameter x 6m length RSB?
9.468
9.909
9.280
9.017
The authority to approve the termination of contract for the Regional Projects.
Undersecretary for UPMO and/or Technical Services
The incumbent RD
The incumbent DE
The incumbent Regional Engineer
Welcome arc/overhead boundary marker shall be provided with minimum vertical clearance of ______?
4.88m
5.03m
5.33m
5.50m
For overhead utility and power lines crossing the roadway, vertical clearance shall not be less than _____ from roadway surface.
4.88m
5.03m
5.33m
5.50m
For overhead utility and power lines from surface of sidewalks, vertical clearance shall not be less than _____
4.88
5.03
5.33
5.5
Structure at the two ends of a bridge use for transferring the loads from the bridge superstructure to the foundation bed and giving lateral support to the embankment.
Approach Slab
Wing Wall
Abutment
Pier
How many percent is the Roadway Cross Slope for a Portland Cement Concrete Pavement (PCCP)?
0.5%
1.0%
1.5%
2.0%
What is the minimum width of a road shoulder?
0.8 m
1.0m
1.5m
2.0m
How many percent is the Shoulder Cross Slope for a Gravel Surfacing?
3.0%
2.5%
2.0%
1.5%
Gutters, Valleys, Flashings Hip and Ridge Roll shall be fabricated from ___ cold rolled plain galvanized iron sheets.?
Gauge 22
Gauge 24
Gauge 26
Gauge 28
Which of the following Gauge No. of Galvanized Iron Sheets is the thickest?
Gauge 22
Gauge 24
Gauge 26
Gauge 28
What is the minimum end lap of Pre-painted Metal Sheets for Roofing Application?
300mm
250mm
200mm
150mm
What is the minimum end laps of Pre-painted Metal Sheets for Walling Application?
250mm
200mm
150mm
100mm
What is the cement/sand ratio to achieve 1,000 psi of concrete spacer?
1:2
1:3
1:4
1:6
What is the duration on the removal of forms and shoring of suspended slab and beams?
3 days
7 days
14 days
21 days
What is the concrete proportion (cement: sand: gravel) for Footings, Beams and Columns?
1:2:3
1:2:4
1:2.5:5
1:3:6
What is the concrete proportion (cement: sand: gravel) for Floor, slabs and ramps?
1:2:3
1:2:4
1:2.5:5
1:3:6
What is the minimum distance of a school building from a cliff?
20 m
10 m
8 m
6 m
What is the minimum distance of a school building from a power line tower?
20 m
10 m
8 m
6 m
What is the height distance between the center of the outlet and the flooring surface?
200mm
300mm
400mm
500mm
What is the height distance between the center of the switch and the flooring surface?
1.2m
1.3m
1.4m
1.5m
Soil or earth material which has been deposited by running water.
Alluvial
Mud
Silt
Sludge
A horizontal strip or shelf built into an embankment or cut, to break the continuity of an otherwise long slope
Berm
Bench
Trial Strip
Landing
A structure under a road, railway or embankment, whether of single or multiple barrel construction, generally with a width of less than five (5.0) meters per opening measured between inside wall faces.
Cut-off channel
Cutoff
Culvert
Drainage
An alternative method of procurement of goods from the previous winning bidder, whenever there is a need to replenish goods procured under a contract previously awarded through competitive bidding. a) Repeat order
Repeat Order
Limitted Source Bidding
Direct Contracting or Single Source Procurement
Negotiated Procurement
Particles that pass through a number 4 sieve (4.75mm) and retained on a number 200 sieve (0.075mm).
Silt
Sand
Clay
Peat
What is the longitudinal grade for roads?
Minimum of 0.50% on cut & maximum of 12% on cut/fill section
Minimum of 01.00% on cut & maximum of 10% on cut/fill section
Minimum of 1.50% on cut & maximum of 12% on cut/fill section
Minimum of 1.00% on cut & maximum of 10% on cut/fill section
What is the maximum permissible variation in actual weight of a steel bar from the theoretical weight?
6%
7%
8%
9%
What is the maximum permissible variation in actual weight of a steel bar from the theoretical weight?
7,900 kg/m^3
7,800 kg/m^3
7,850 kg/m^3
8,000 kg/m^3
What is the rate of application of a curing compound on Portland Cement Concrete Pavement (PCCP)?
4 Liters to not more than 10 m^2
4 Liters to not more than 15 m^2
4 Liters to not more than 13 m^2
4 Liters to not more than 14 m^2
Concrete on area represented by cores will be considered adequate if the average strength of the cores is equal to at least 85%, and no single core is less than ____ of the specimen strength. a) 85%
85%
75%
70%
50%
The criteria for foundation of a school building for the actual soil bearing capacity on natural ground is ____ at depth of 1.5 m. Less than this value is subject for a changed in foundation.
94 kPa
95 kPa
96 kPa
97 kPa
For pavement design purpose, the varying axle loads are converted to a common denominator which is in terms of…
18,000 lbs (80 kN) single axle load
10,000 lbs. (44 kN) wheel load
24,000 lbs. (107 kN) tandem axle load
32,000 lbs. (142 kN) standard axle load
The minimum pavement width of carriageway for a national road shall be _____?
5 m for two lanes
5.8 m for two lanes
6.1 m for two lanes
6.7 m for two lanes
What is the prescribed concrete structure for a bridge with span of 13-20 meters
Flat slab bridge
Reinforced concrete deck girder (RCDG) bridge
Prestressed concrete girder (PSCG) bridge
Cable bridge
{"name":"PAMPASA NG FE", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"In accordance with the requirements of Geotechnical investigation, what is the minimum number of boring shall be provided for piers or abutments over 30m wide?, For school buildings, all slab reinforcements shall be ____ minimum for bottom and top slab, For school buildings, camber all beams and girder atleast 6mm every ___ span, except cantilevers for which the camber shall be as noted in the plans but no case less than 20mm for every ____ span","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}
More Quizzes
Valentine Application
3225
Sales Cloud Cerification
139700
Quiz 1.1
10530
Serial Quizzer Day 2
520
Just My Imagination & The Temptations Trivia - Free
201033306
Typography Anatomy - Free Type Terms Practice
201019562
Logo: Name These Famous Brands - Free Online
201029717
Am I Too Nice? - Free Self-Assessment
201021680
SpongeBob Trivia - Ultimate Questions with Answers
201029106
Cellular Respiration & Photosynthesis - Free Practice
201021824
What Type of Depression Do I Have? Take the Free
201023950
Think You Can Ace Place Value of Whole Numbers?
201038687