Prince2 Foundation Exam

What does PRINCE2 stand for?
Projects in Controlled Environments
Project Management Institute
Programmed Integrated Environment
Professional Integration of Enterprise
Which of the following is NOT a PRINCE2 principle?
Continued Business Justification
Learn from Experience
Manage by Exception
Focus on Products
Tailor to Suit the Project Environment
Who can be appointed as the Executive in a PRINCE2 project?
The Senior User
The Project Manager
The Senior Supplier
The Customer
The Team Manager
Which document outlines the overall plan for the project and includes information such as timelines, budgets, and resources required?
Business Case
Risk Register
Project Initiation Documentation
Project Plan
Which of the following is NOT one of the seven themes in PRINCE2?
Quality
Change
Progress
Organization
Risk
Plans
Business Case
What is the purpose of the Daily Log in PRINCE2?
To track progress against the project plan
To record issues and risks
To provide a summary of the project status
To capture daily updates and actions
Which of the following is NOT a type of tolerance in PRINCE2?
Time
Cost
Scope
Quality
Benefit
Risk
What is the purpose of a Work Package in PRINCE2?
To define the overall scope of the project
To provide detailed information on how to complete a specific task
To capture risks and issues
To outline the roles and responsibilities of team members
Which of the following is NOT a role in PRINCE2?
Project Manager
Business Analyst
Team Manager
Executive
Senior User
Senior Supplier
Which document outlines the justification for the project and includes information such as costs, benefits, and risks?
Business Case
Project Initiation Documentation
Project Plan
Risk Register
Who is responsible for creating the Daily Log in PRINCE2?
The Project Manager
The Executive
The Senior User
The Senior Supplier
Which of the following is NOT an element of the PRINCE2 process model?
Starting up a Project
Initiating a Project
Directing a Project
Managing a Stage Boundary
Closing a Project
Controlling a Stage
What is the purpose of the Product Description in PRINCE2?
To provide a summary of the project status
To capture daily updates and actions
To outline the roles and responsibilities of team members
To provide detailed information on a specific product
Which of the following is NOT a PRINCE2 theme?
Quality
Change
Progress
Organization
Risk
Plans
Scope
What is the purpose of the Lessons Log in PRINCE2?
To capture risks and issues
To track progress against the project plan
To provide a summary of the project status
To record lessons learned throughout the project
Who is responsible for creating the Project Initiation Documentation in PRINCE2?
The Project Manager
The Executive
The Senior User
The Project Board
Which of the following is NOT an element of the PRINCE2 principles?
Continued Business Justification
Learn from Experience
Manage by Exception
Focus on Products
Tailor to Suit the Project Environment
Defined Roles and Responsibilities
What is the purpose of the Issue Register in PRINCE2?
To provide a summary of the project status
To capture daily updates and actions
To outline the roles and responsibilities of team members
To track and manage issues throughout the project
Which of the following is NOT a type of risk response in PRINCE2?
Avoid
Transfer
Accept
Mitigate
Exploit
Enhance
What is the purpose of the Change Authority in PRINCE2?
To approve changes to the project plan
To manage risks and issues
To provide a summary of the project status
To ensure that all team members are following the correct processes
Which document outlines the roles and responsibilities of each team member in the project?
Project Initiation Documentation
Risk Register
Communications Management Strategy
Roles and Responsibilities Matrix
Who is responsible for creating the Benefits Review Plan in PRINCE2?
The Project Manager
The Executive
The Senior User
The Project Board
Which of the following is NOT an element of the PRINCE2 themes?
Quality
Change
Progress
Organization
Risk
Plans
Time Management
What is the purpose of the Product Breakdown Structure in PRINCE2?
To provide a summary of the project status
To capture daily updates and actions
To outline the roles and responsibilities of team members
To break down the project into manageable products
Which of the following is NOT a type of issue in PRINCE2?
Exception
Off-Specification
Request for Change
Risk
Problem
Query
What is the purpose of the Configuration Item Record in PRINCE2?
To provide a summary of the project status
To capture daily updates and actions
To outline the roles and responsibilities of team members
To track changes to products throughout the project
Who is responsible for creating the Communication Management Strategy in PRINCE2?
The Project Manager
The Executive
The Senior User
The Project Board
Which of the following is NOT an element of the PRINCE2 process model?
Starting up a Project
Initiating a Project
Directing a Project
Managing a Stage Boundary
Closing a Project
Controlling a Product
What is the purpose of the Risk Register in PRINCE2?
To provide a summary of the project status
To capture daily updates and actions
To outline the roles and responsibilities of team members
To track and manage risks throughout the project
Which of the following is NOT a type of product in PRINCE2?
Business Case
Project Plan
Benefits Review Plan
Change Authority
Quality Register
Issue Report