Complexity Quiz

The majority of the work done by a typical Scrum Team will most likely fall in which domain?
Chaotic
Complex
Complicated
Obvious
When facing a large project with obvious, complicated, and complex parts, which should the Product Owner put at the top of the backlog?
Complicated
Complex
Obvious
Whatever the stakeholders ask for first
Less effective organizations tend to oscillate between which two domains?
Obvious and Chaotic
Obvious and Complicated
Complicated and Complex
Complex and Obvious
Which of the following would be a good example of a Complicated Product Backlog Item.
Get the ecommerce website that has gone down back up and running.
Get the ecommerce website that has gone down back up and running.
Install an upgrade to a commonly used software system.
Purchase a computer for a new employee.
Which of the following definitions of a Sprint most align with Complexity?
A 1-4 week project
A 1-4 week milestone
A 1-4 week delivery of value
A 1-4 week experiment
{"name":"Complexity Quiz", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"The majority of the work done by a typical Scrum Team will most likely fall in which domain?, When facing a large project with obvious, complicated, and complex parts, which should the Product Owner put at the top of the backlog?, Less effective organizations tend to oscillate between which two domains?","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}