7 Communications Quiz

After a major problem in the design has been found, the project team has been asked to provide information on the problem.  What is the best method to do this?
Written and formally 
Informally and written 
Verbally and formally 
Informally and verbally 
After watching Steve give a progress report, the senior project manager tells him that he needs to attend a communication skills class. Steve says that he planned the presentation in detail and asks what the difference is between communication skills and communication management?
Communication skills are techniques while communication management is a plan. 
Communication skills are a plan while communication management is a tool. 
They are the same thing. 
Communication skills are a subset of the communication plan. 
An example of a 'Pull communication' method is
Knowledge repositories
Meetings
Video conferencing
Press releases
An important output of the control communications process is:
Work performance information
Project communications
Performance reporting
Issue log
Communication Methods such as Interactive, Push and Pull are very important to Project Success. The push method is for canned communications and are typically sent from one individual to multiple receivers. This method of communication is best when used for;
Delivering Status Reports
Encouraging Discussion
Providing Training
Resolving conflict
In which Project Management Process is the storing, retrieving, and disposition of project information handled?
Manage communications
Control communications
Manage Stakeholder Engagement
Plan communications management
Managing communications includes a number of tool and techniques for effective communication. Which of the following is not considered a part of these?
Frequency of communications
Choice of media
Active listening
Writing styles
The most successful project managers will spend a significant amount of time doing which of the following:
Communicating
Managing risks
Directing and managing the work
Updating various plans
The new project manager is concerned about what part of the project he should focus  on the most once he is in the direct and managing . His mentor tells him that he should focus  and spend most of his time on which of the following?
Communicating with the team and stakeholders
The project management plan 
Managing the team 
Preventing scope creep 
The project is beginning to fail and the project manager needs to deliver the news. What should the project manager do to inform the PMO office?
Put the information in the context of the project progress. 
Tell a joke 
Inform them as late as possible.
Inform the customer first. 
{"name":"7 Communications Quiz", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"After a major problem in the design has been found, the project team has been asked to provide information on the problem.  What is the best method to do this?, After watching Steve give a progress report, the senior project manager tells him that he needs to attend a communication skills class. Steve says that he planned the presentation in detail and asks what the difference is between communication skills and communication management?, An example of a 'Pull communication' method is","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}