SAP Activate Project Manager
SAP Activate Project Manager Quiz
Test your knowledge and skills on the SAP Activate project management methodology with this comprehensive quiz designed for professionals and enthusiasts alike.
Whether you are looking to enhance your understanding or prepare for certification, this quiz covers crucial aspects of SAP S/4HANA, Agile delivery, and more.
- 80 engaging questions
- Multiple-choice format
- Immediate feedback on your answers
2.When does the Scrum Team receive formal confirmation that the User Stories are completed to the satisfaction of the Product Owner?
During the Sprint Review
During the User Acceptance Test
During the Sprint Retrospective
During the daily Scrum meeting
3.Where can you find Data Migration templates?
SAP Cloud Appliance Library
SAP Roadmap Viewer
SAP S/4HANA Migration Cockpit
SAP Best Practices Explorer
4.Which of the following belong to the Application Design andConfiguration workstream for SAP S/4HANA Cloud in the Explore phase? Note: There are 2 correct answers to this question.
Configuration definition
Kick-off workshop
Integration prerequisites confirmation
Fit-to-standard workshop
5.What is the key characteristic of the Agile project approach?
Frequent and detailed project scheduling
Iterative build with frequent inspections
Formal and detailed documentation
Frequent Quality Gates
6.What is the recommended integration bus in the cloud?
SAP Best Practices Explorer
SAP Cloud Platform Integration
SAP API Business Hub
SAP Process Orchestration
7.Which Value Chains does SAP Solution Manager 7.2 deliver? Note: There are 3 correct answers to this question.
Hire-to-Retire
Requirements-to-Deploy
Cash-to-Order
Request-to-Fulfill
Detect-to-Correct
8.Which estimation technique can be used in Agile Delivery Approach to size the User Stories during Sprint Planning?
Detailed bottom-up effort estimate that breaks each User Story up into hours or shorter tasks
Detailed bottom-up effort estimate by the Scrum Master in Story Points based on the User Story complexity
Product Owner's relative estimate of the effort that will be needed to implement the User Story
Relative estimate in Ideal Person Days that reflects the best estimate provided by the project team
9.What criterion does the Product Owner use to sequence the Product Backlog?
Business priority
Resource availability
Complexity
Relative effort
10.Which of the following are part of the 10 SAP Quality Principles? Note: There are 2 correct answers to this question.
Start scoping early.
Plan one phase at a time.
Use standard functionality optionally.
Achieve production readiness.
11.What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud?
SAP Support Marketplace
SAP Roadmap Viewer
SAP Transformation Navigator
Implementation portal for SAP S/4HANA Cloud
12.What does the Side-by-Side Extensibility Option mean?
There are two SAP S/4HANA instances: one for standard code, and another for custom developments.
Extensibility is based on the SAP Cloud Platform and published APIs.
SAP S/4HANA extensions are context-aware and focused on tight integration.
Reporting is transferred to BW/4HANA.
13.What does a Cutover involve?
Transporting new Product Increment in the Development System
Switching productive business operations from one system to another
Closing Quality Gate
Presenting completed User Story to Key Users
14.In which phase will the customer develop a preliminary strategy for building a target Operations and Support organizational model?
Discover phase
Explore phase
Run phase
Prepare phase
15.Where can you find the Integration Content? Note: There are 3 correct answers to this question.
SAP Cloud Appliance Library
SAP API Business Hub
Cloud Integration Automation Service
SAP Solution Manager
SAP Best Practices Explorer
16.How would you describe the Realize phase in the “New Implementation of SAP S/4HANA" transition path?
Configure
Configure and adjust custom code
Configure and develop
Configuration copy
17.What is the term used for workshops, which are intended to set value targets, validate SAP Standard fun ctionality against customer requirements, and collect delta requirements in the “New Implementation of SAP S/4HANA” transition path?
Backlog Grooming
Solution Validation
Design Thinking
Delta Design
18.What are the responsibilities of the Product Owner in Release and Sprint Planning? Note: There are 2 correct answers to this question.
Prioritize backlog User Stories by business priority.
Analyze the functional and technical dependencies between User Stories
Define objectives for each Release.
Estimate the backlog User Stories.
19.Which role is responsible for defining the dataset structure and its data usage in alignment with requirements from all business fun ctions?
Data Volume Management Consultant
Master Data Change Requester
Business Data Owner
System Administrator
20.What are some activities in the Requirements-to-deploy scenario within SAP Solution Manager? Note: There are 2 correct answers to this question.
Walkthrough for Wave
SAP Model Company demo for every Wave
User Acceptance Test every Sprint
Demo for Sprint
21.What technique helps a Scrum Team to prioritize a large, flat Backlog?
Retrospective
User Story Mapping
Planning Poker
Fit/Gap Analysis
22.What is the objective of a Sprint Retrospective meeting?
Improve the Scrum process.
Provide formal feedback to the Project Manager.
Define the stakeholder management approach.
Review and prioritize the Backlog.
23.Ready-to-use Content in SAP Activate includes which of the following? Note: There are 2 correct answers to this question.
Business models from leading companies in each industry sector
Courses delivered by SAP Education
Project Accelerators
SAP Best Practices
24.Which of the following scenarios are enabled for the "Selective Data Transition" transition path with the SAP Landscape Transformation tool? Note: There are 3 correct answers to this question.
Extraction of Business Units
System Consolidation
Consolidation through online data replication
Security Migration
System Upgrade
25.What is the primary purpose of the SAP Activate Methodology?
To provide the sequence of actions in the project
To manage solution documentation
To enable access to the SAP Ecosystem
To provide end-to-end Application Lifecycle Management
26.What SAP Solution Manager capability in the Change Control Management process is used to synchronize changes between SAP ERP and SAP S/4HANA maintenance tracks?
Business Process Change Analyzer
SAP Code Vulnerability Analyzer
Dual Landscape Synchronization (Retrofit)
SAP Code Inspector
27.Which of the following are levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package? Note: There are 2 correct answers to this question.
Scope Items
Configuration Guides
Business Process Scenarios
Building Blocks
28.What are some important accelerators (guides, templates) that could help establish the Test Management Process in an SAP S/4HANA project? Note: There are 2 correct answers to this question.
Data Migration Strategy
Test strategy
SAP Support Standards
SAP Transformation Navigator
29.What are some of the key characteristics of the implementation approach in SAP Activate Methodology? Note: There are 2 correct answers to this question.
Based on Ready-to-use Content
Cloud Ready
On premise only
Fixed scope
30.In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps?
Realize
Deploy
Prepare
Explore
31.What is the best target deployment option of SAP S/4HANA for the “System Conversion” transition path?
SAP S/4HANA Cloud
SAP C/4HANA
SAP S/4HANA
Hybrid of SAP S/4HANA Cloud and SAP S/4HANA
32.Which of the following tools are specific to the Data Management workstream? Note: There are 3 correct answers to this question.
SAP Landscape Transformation
SAP Roadmap Viewer
SAP Data Services
SAP S/4HANA Migration Cockpit (for both SAP S/4HANA Cloud and SAP S/4HANA editions)
SAP Solution Manager
33.What is SAP Activate?
A bundle of ASAP, SAP Launch, and Rapid Deployment Solutions
Step-by-step instructions on how to move from SAP Best Practices to your custom solution
A methodology for each of the deployment modes (cloud, on premise, hybrid)
A Solution Adoption Framework
34.What tool can you use to collaborate with other SAP Activate Methodology practitioners?
SAP Jam
SAP Solution Manager
SAP Implementation Assistant
SAP Roadmap Viewer
35.What accelerator can help you document the Configuration Definition in the Explore phase?
Test Strategy
Change Request template
Data Definition
Backlog template
36.What tool provides sizing estimations for the “System Conversion” transition path?
SAP Best Practices Explorer
SAP Readiness Check
Scope and Effort Analyzer
SAP Transformation Navigator
37.Via which media does SAP provide Ready-to-run systems for SAP S/4HANA deployments? Note: There are 2 correct answers to this question.
SAP App Center
SAP Cloud Appliance Library
Blu-ray disks
SAP Solution Builder tool
38.Why are Scaling Scrum techniques used to coordinate large teams in complex projects?
To make test case execution as difficult as possible
To manage the flow of information between the project and stakeholders
To staff as many people as possible on the project to increase utilization
To ensure alignment in architecture, configuration, and integration
39.Which artifacts in the Testing workstream are created within the Realize phase for the “New Implementation of SAP S/4HANA Cloud” transition path? Note: There are 2 correct answers to this question.
Reporting Functional Specifications
Functional Specifications
User Acceptance Test - Plan
Functional Test Scenarios
40.In the "New Implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape? Note: There are 2 correct answers to this question.
QAS
DEV
P-system
Starter system
41.Which of the following are examples of Ready-to-run SAP S/4HANA systems? Note: There are 2 correct answers to this question.
Development system with activated SAP Best Practices
Fully Activated Appliance
SAP Mission Control Center
SAP Best Practices Explorer
42.What Sprint types are part of the SAP Activate Methodology? Note: There are 3 correct answers to this question.
Initial
Build
Daily
Firm-up
Foundational
43.What is the purpose of a Firm-up Sprint?
To run an end-to-end Integration Test
To revise the Release Plan and Sprint Plan
To perform a String Test
To demonstrate functionality from previous Sprints
44.You are defining the Testing Strategy for your project. What would you include in a Scope of Integration test?
The connectivity between database and application servers
The functionality of Modular Process
The functionality of End-to-End business processes
The network communication
45.Which new project roles are introduced with the SAP Activate Methodology for the Agile delivery approach, compared to Waterfall? Note: There are 2 correct answers to this question.
Integration Lead
Product Owner
Design Thinking Coach
Scrum Master
46.What is the basis for approving work results (signing Act of Acceptance) on a Project Phase level?
Scrum of Scrums meeting decision
Definition of Done for User Story
Agreed and met Acceptance Criteria within Quality Gate
Definition of Ready for Sprint
47.Who determines the tasks that are required to complete the committed Backlog Items in a Sprint?
Scrum Team
Product Owner
Project Manager
Scrum Master
48.What tool provides guidance on replacing custom code developed for SAP ERP with SAP S/4HANA fun ctionality for the “System Conversion” transition path?
Simplification Item Check (SI-Check
SAP Code Inspector
Software Update Manager with Database Migration Option
Software Provisioning Manager
49.Which of the following is part of the Explore phase in the “New Implementation of SAP S/4HANA Cloud” transition path?
Simplification and Custom Code Impact Analysis
Solution Validation and Delta Design
Setup and Enablement
Fit-to-standard
50.Which end-to-end turn-key Application Lifecycle Management (ALM) solution can support you in managing requirements and software development for large Agile projects?
Change Request Management
Solution Manager Test Suite
Requirement Management
Focused Build
51.How do you set up Scrum teams? Note: There are 2 correct answers to this question.
Based on End-to-End Processes like Order-to-Cash
As a cross-functional team covering multiple functions, like configuration, data loads, and testing
By type of work, like configuration Scrum, documentation Scrum, and testing Scrum.
Based on group size, but a minimum of 12 people
52.Which collaboration features can SAP Jam users access in the SAP Methodologies Jam group? Note: There are 2 correct answers to this question.
Ask questions
Update Key Deliverable wikis
Comment on Key Deliverables
Tweet questions
53.Which accelerators support the Fit-to-standard workshop in the Explore phase? Note: There are 2 correct answers to this question.
Test Strategy
Backlog template
Business-Driven Configuration Questionnaire
Quality Gate Checklist
54.In which phase should you first run the SAP Readiness Check for SAP S/4HANA in a "Selective Data Transition" transition path, in a System Consolidation scenario that includes conversion from SAP ERP?
Prepare
Realize
Discover
Explore
55.What is a Strategy Level 0 (L0) artifact?
Project result that is developed solely by the partner
Preliminary strategy developed by the customer to approach the project in a specific workstream
Approach document that is developed by a united Project Team (partner + customer)
Optional information that is NOT important for project activities
56.Which tools offer support for the technical implementation of SAP Fiori? Note: There are 3 correct answers to this question.
SAP Fiori launchpad content manager
KPI Catalog
Industry Value Maps
Task lists for rapid activation
SAP Fiori apps reference library
57.What is Scrum of Scrums?
Integration meeting among the various Scrum teams
Alternative to regular Scrum process for smaller teams
Mechanism for gathering and validating requirements
Frequent inspection of code and configuration prior to Quality Gates
58.According to the Definition of Done, which activity must be completed for each Sprint?
The solution must be built and configured in the development system (DEV).
Functionality must be tested in the Production System (PROD).
End-user training must be delivered.
Functionality must be released to the business.
59.Which of the following are benefits of using Ready-to-use Content? Note: There are 2 correct answers to this question.
Exhaustive solution documentation
Predictable results
Minimized Total Cost of Ownership
Fast Time-to-Value
60.Which Scrum role is part of a Full Scrum Team in the SAP Activate Methodology?
Application Consultant
Product Owner
Project Manager
System Administrator
61.In which phase should you create a Data Migration Strategy (L0) during a Selective Data Transition?
Deploy
Realize
Explore
Discover
62.What Solution Operations Framework can customers use to create a joint Business and IT organization?
Business Transformation Management Methodology
Customer Center of Expertise
SAP Leonardo
SAP Activate
63.What is the difference between the “System Conversion” and the “New Implementation of SAP S/4HANA” transition paths? Note: There are 2 correct answers to this question.
SSCUIs are used in System Conversion for configuring SAP S/4HANA through the Manage Your Solution app.
In the Realize phase, custom code is adjusted rather than developed for System Conversion.
In the Realize phase, data is converted and NOT migrated for System Conversion
There are different upgrade cycles.
64.What information does the Project Team need before they can correctly estimate the relative size of backlog User Stories?
Available project resources
Overall project schedule
Definition of Done
Test Strategy
65.Which of the following best outlines the sequence oftesting within the Application Design and Configuration workstream in the Realize phase?
Integration Test . User Acceptance Test . String test
String test. Integration Test. User Acceptance Test
String test. User Acceptance Test. Integration Test
Data Migration. String test. User Acceptance Test
66.Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?
User Stories are in Ready state for only the first 2 to 3 Sprints.
Go-Live scope is fixed on the first of January the following year.
Project scope and planning are completed and final.
Timelines of the Sprint may differ due to the workload.
67.What is the difference between the “New Implementation of SAP S/4HANA Cloud” and the “New Implementation of SAP S/4HANA” transition paths? Note: There are 2 correct answers to this question.
Different sets of workstreams are used for these transition paths.
There are different roles in the Application Design and Configuration workstream.
SAP S/4HANA uses the Implementation Guide (IMG) and the In-App Extensibility Option for configuration and development, and SAP S/4HANA Cloud uses SSCUIs and the Side-by-Side Extensibility Option.
Upgrades of SAP S/4HANA Cloud are managed by SAP, and upgrades of SAP S/4HANA are managed by the customer.
68.Which activity helps the Project Team add User Stories to the Product Backlog?
Assessing project risks
Preparing a project schedule
Planning the User Acceptance Test
Conducting the Solution Validation workshop
69.In which phase do you create “an ordered list of everything that is known to be needed in the product”?
Prepare
Explore
Realize
Deploy
70.What does the Content element of SAP Activate provide? Note: There are 3 correct answers to this question.
Migration Content
Functional Specifications for WRICEF development
Business Processes Content
Integration Content
End-User guides
71.What capabilities does SAP API Business Hub provide to help you select integration options for your project? Note: There are 3 correct answers to this question.
Sandbox for testing APIs
Recommendations on using integration bus (SAP PO or SAP CPI)
Pre-packaged integrations
Integration with IDE and Code Generation
Advice on selecting Scope Items in SAP Best Practices Explorer
72.Which artifacts are part of the Solution Adoption workstream? Note: There are 3 correct answers to this question.
Project Business Case
Business Transformation Review (Point of View)
Project Plan
System GoLive Announcement (order)
Detailed Design – Business Process
73.In SAP Activate, what tool is used in the Agile Delivery Approach during the Realize phase to make forecasts based on actual data?
Burndown Chart
Project Plan
Product Increment
Release Plan
75.What is the purpose of the Scrum Board?
To visualize team progress
To manage the resource load
To document the results of the Integration Test
To show the functional breakdown of the solution scope
76.What is the purpose of the Solution Validation activity in the Explore phase? Note: There are 3 correct answers to this question.
Verify technical installation.
Challenge changes to standard.
Log additional scope items.
Identify gaps.
Educate project participants.
77.Which artifacts are created within the Application Design and Configuration workstream in the Explore phase of the “New Implementation of SAP S/4HANA” transition path? Note: There are 3 correct answers to this question.
Organization Structure Specification
Roles and Authorizations Management Concept
Delta Requirements List – Register
Project Procedure – Mock-up Modeling
Detailed Design – Business Process
78.What are some of the key topics covered in the Customer Team Enablement workstream? Note: There are 3 correct answers to this question.
Project Sourcing Approach
Project Management
Technical Expertise
Planning Skills
Solution Expertise
{"name":"SAP Activate Project Manager", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Test your knowledge and skills on the SAP Activate project management methodology with this comprehensive quiz designed for professionals and enthusiasts alike.Whether you are looking to enhance your understanding or prepare for certification, this quiz covers crucial aspects of SAP S\/4HANA, Agile delivery, and more.80 engaging questionsMultiple-choice formatImmediate feedback on your answers","img":"https:/images/course5.png"}