PPSTM QUIZ 2

A vibrant and modern illustration of project management concepts, featuring elements like timelines, Gantt charts, and teamwork in a corporate setting.

PPSTM Project Management Quiz

Test your knowledge on project management principles with our engaging PPSTM quiz! This quiz covers essential topics such as critical paths, dependencies, and activity management.

  • Multiple choice questions
  • Focuses on real-world scenarios
  • Designed for project management enthusiasts
11 Questions3 MinutesCreated by AnalyzingWave542
Enter your name and last three digits of enrollment no. (e.g. Mukhtar 099)
A dependency requiring that design be completed before manufacturing can start is an example of a (n)
Discretionary dependency
External dependency
Mandatory dependency
Scope dependency
Which of the following is CORRECT?
The critical path helps to prove how long the project will take.
There can be only one critical path
The network diagram will change every time the end date changes.
A project can never have negative float.
A project has three critical paths. Which of the following BEST describes how this affects the project?
It makes it easier to manage.
It increases the project risk.
It requires more people.
It makes it more expensive.
An Activity has an Early Start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9 and a late finish (LF) of day 19. The activity:
Is on the critical path.
Has a lag
Is progressing well.
Is not on the critical path.
You’re managing a nationwide telecom deployment project. You learned that you’re unable to start any civil works before obtaining a government agency’s permit, which could take months. The project deadlines are aggressive and you might face penalties if you don’t meet them. Obtaining the government agency’s permit prior to civil works on any site is an example of which of the following?
External dependency
Mandatory dependency
Project constraint
Project requirement
Which of the following is NOT a tool and technique of Define Activities?
Decomposition
Rolling Wave Planning
Milestones
Expert judgement
You’re managing a software development project. You want to create the basis that will be used later on for estimating, scheduling, executing, monitoring and controlling the project work. Which process performs this activity?
Create WBS
Define Scope
Define Activities
Create Project Management Plans
A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
Finish-to-Start
Start-to-Finish
Start-to-Start
Finish-to-Finish
Which of the following is NOT an input to the Sequence Activities process:
Project Scope Statement
Activity Attributes
Activity list
Change requests
Identification of Mandatory Dependecies is BEST done during which process?
Sequence Activities
Develop Schedule
Define Activities
Estimate Activity Duration
{"name":"PPSTM QUIZ 2", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Test your knowledge on project management principles with our engaging PPSTM quiz! This quiz covers essential topics such as critical paths, dependencies, and activity management.Multiple choice questionsFocuses on real-world scenariosDesigned for project management enthusiasts","img":"https:/images/course5.png"}
Powered by: Quiz Maker