Energy Week- 3rd Quiz

Employee Name
Employee ID
What is the total % SPC share of utility 1, 2 & 3 in FY 2017-18 (Till Nov)?
32
19
12
31
In FY 2017-18 which month is best in term of SPC?
Aug-2017
Jul-2017
Sep-2017
Nov-2017
What is the % reduction in SPC from FY 2013-14 to FY 2017-18 (Till NOV)?
31%
69%
36%
56%
What is the % share of solar generation of Khandala plant in FY 2017-18 till NOV-17 of total units consumed?
24.33%
29.3%
15.66%
36%
Among all the blocks which block has the best % reduction in SPC till FY 2017-18 as compare to FY 2013-14?
Utility-3
Utility-1
WPB
Lighting
If we avoid unwanted operation of 5 no’s WPB mixer agitators at full load for 2 Hrs in a day how much will be the SPC reduction assuming a production of 700kl of paints?
0.78
1
1.27
1.5
How much KWH will be saved if 80% loaded WPB NIEMEN TSD’S cycle time is reduce by 20 Min?
100
300
75
0
Where “Vacuum pumps” has been installed in plant?
Packing & ASRS
WPB Process
SPB Process
Utility-1
Height adjustment done in auto through DCS, Unwanted running eliminated, Stopping if powder addition hold for 5 min, Tip speed optimization, Grinding time reduction for some products, Part thickener addition etc. All these particular changes are related to which equipment of the plant?
TSD
Compressor
Packing M/c
Chillers
What is the Installed capacity of Solar & Wind in Khandala plant?
4000 KW & 18 KW
4MW & 18 MW
4 KW & 18 MW
400 KW & 18 KW
Through wind & Solar power generation approximately how much Rs. Khandala plant have saved till Nov-2017?
58486014
58261776
58486104
58468014
What is the objective of “RE36”?
By 2020 sourcing 36% of Electricity requirement from renewable sources
By 2020 sourcing 18% of Electricity requirement from renewable sources
By 2020 sourcing 36% of Electricity requirement from Non-renewable sources
By 2020 sourcing 36MWh of Electricity requirement from renewable sources
What is the installed capacity of renewable sources for Asian Paints till FY2016-2017?
15.58 MW
18.6 MW
36 MW
22 MW
Till date which is the best month in terms of plant SPC?
Mar-2016
Aug-2017
Feb-2016
Sep-2017
What is the YTD SPC of Khandala till Nov-2017 ?
81.45
76.29
87.44
75