Final Exam 2
The most important output of Define Scope is
Scope Statement
Statement of Work
Requirements Documents
WBS Statement
You and the project sponsor are developing requirements for an internal project. The charter will include all except the following?
Detailed timeline
High level budget
Project requirements for approval.
Statement of work
You are defining the initial scope of a new project as for an external customer. All of the following are items that you will use for the initial inputs except?
Expert judgement
Business case
Government standards
Social need
You are a project manager for XYZ. You are working on a project to expand the manufacturing capacity for your department. The construction of the new facility will be outsourced to ABC. Who approves the project charter for this project?
The project sponsor at XYZ
The project sponsor at ABC Inc.
The finance department at XYZ.
The project manager at XYZ.
You are working as a part-time project coordinator for a software company. You find, however, that a significant part of your effort is to get a certain developer from another department. What type of company are you working for?
Functional
Projectized
Multinational
Strong matrix
Your new assistant is reviewing the project charter which discusses that the project needs to meet certain government regulations and industry standards. She asks you what the difference is between a standard and a regulation.
Regulations are required while standards are optional.
Government regulations are optional and standards are required.
Standards are guidelines and regulations are only suggested practices.
Regulations are sometimes required and standards are recommended practices.
Adam is the project manager for the MAX Project. It is a large multi-year project and he is breaking down the project into phases. What is the best reason why a project be broken down into phases?
Provide more defined management and control of the project as a whole or that deliverables have to be completed in a certain order.
Define the scope for each phase.
Identify the required work that is needed within each phase.
Identify the specialized resources needed for each phase.
The project charter you are working on is being changed frequently by two of the stakeholders. Who has the primary responsibility to decide if these changes are necessary?
Project sponsor
Change control board
Project manager
Project team
An organization is forming a new project office. The new manager has decided to use formal project charters. As an experienced project manager, why would you encourage this practice?
The project charter authorizes you to use organizational resources to accomplish the objectives of the project.
The project charter allows you to establish the business need for the project.
The project charter ensures that a preliminary budget and schedule are developed.
The project charter allows you to get senior management buy-in for your project management approach.
Bill is working on making a list of assumptions for the project charter. Why is this list important?
Assumptions are a tool of risk identification.
If anything goes wrong, this list provides accountability.
Assumptions allow the project team to have a baseline to work with.
Assumptions limit the project team on what decisions they have to make.
Subject matter experts are utilized in a variety of process groups. When do they first get used.
Initiation
Planning
Execution
Closing
Which statement is true about the difference between a project coordinator and a project expediter?
The expeditor works as an assistant and communications coordinator
The coordinator does not make decisions.
The coordinator has no authority.
The expeditor makes final decisions.
The project sponsor has not had formal sign-off on the proposed project. She has told you that you should begin working on the project planning process now. What is your first and best response?
Discuss with project sponsor the possible problems of working without a formal charter.
Begin working on the planning process immediately.
Contact the stakeholders about their priorities.
Work on a project with a charter.
Enterprise environmental factors are a part of the Develop Project Charter process. Which of the following is an enterprise environmental factor?
Marketplace conditions
Maslow's hierarchy of needs
Lessons learned
Expert judgement
You are informed that you will be taking over a poorly managed project. You discover that a charter was never written for this project. How you should proceed?
Work with the sponsor and develop a charter.
Complain to management about the lack of a charter.
Review the project to see if a charter is needed.
Continue without the charter.
The output of identifying stakeholders is which of the following?
Stakeholder register
Stakeholder analysis
Enterprise environmental factors
Power / interest grid
Procurement documents are a part of which initiating process group?
Identify stakeholders
Develop project charter
Plan project procurement
Close procurements
You are working with the PMO office to gather information about why a stakeholder is opposed to the possbile project. This is known as what?
Stakeholder analysis
Identify stakeholders
Expert judgement
Stakeholder register
In what process groups should the stakeholder register be updated?
All but closing
All but planning
All but initiation
All but execution
The project sponsor wants a list of key stakeholders along with their level of authority and their concern about the upcoming project. This is known as what?
Power / Interest grid
Power / Influence grid
Influence / impact grid
Salience model
Bill is gathering information to develop the stakeholder register for a construction project. He is asking which of the following he should not add to the stakeholder register.
A competitor
The local union which has a representative with your company's construction crew.
Local government
The project manager for the client.
Stakeholders can influence the project the most during which process group?
Initiation
Planning
Execution
Closing
You are working on a project in the initial stages and are completing a review of the proposed project charter. You receive news that the project has been cancelled. What is the most likely reason of the selections?
A key stakeholder was not informed of the project.
The communication plan missed a key stakeholder.
The project management plan was not followed.
The project sponsor did not follow the proper template in writing the project charter.
You have identified a mid-level manager to be a key stakeholder in the project you are going to be assigned. He is unaware of the project. What is your best course of action to manage this stakeholder?
Inform him of the project as early as possible.
Inform him once you start planning the project.
Inform him when you start executing the project.
Wait for him to find out on his own.
Stakeholder analysis includes all but which of the following?
Stakeholder register
Identify all the stakeholders
Classify the stakeholders and their impact
Assess stakeholders and how to influence them.
A project team consists of all but which of the following
Competitors
Sellers
Subject matter experts
Customer
You are working for a projectized PMO. What is the best description of this?
Each project has its own staff.
The project manager has some authority over staff that reports to their own functional managers.
The project manager coordinates the staff that has been assigned to the project.
The project manager coordinates the functional managers who provide the staff for the project
What is the main benefit of developing a project management plan?
It creates a central document that defines the basis of the project work.
It creates the project charter.
It contains all the the subsidiary plans.
It manages the project scope.
Which is an input to the develop the project management plan process group?
Outputs from other processes
The project management plan
Facilitation techniques
Change requests
The project management plan contains the baselines for all but which of the following?
Life cycle
Scope
Schedule
Cost
Once the project baselines are created, they may be changed by only what?
When a change request has been approved through the Perform Integrated Change Control process.
When a change request is submitted.
When a change request has been approved by the project manager.
When a change request has been approved by the project sponsor.
You have been asked to begin writing the project scope management plan. You are gathering the necessary documents to begin this process. Which of the following is required to do this?
Stakeholder register
Risk management plan
Focus groups
Requirement traceability chart
The project charter is a key document used throughout the project scope management plan. Which of the process groups does not need the project charter?
Validate scope
Plan scope management
Define scope
Collect requirements
Collecting requirements encompasses a variety of areas for different reasons. Which of the following is not a type of requirement?
Risk requirements
Business requirements
Quality requirements
Stakeholder requirements
Victoria is collecting the requirements for the project scope and a key stakeholder asks to include a requirement which was denied in the charter. What should she do next?
Tell the stakeholder that the requirement was denied while developing the project charter.
Submit the requiement as a change request.
Discuss the request with the project sponsor.
Since this is a key stakeholder, the request should be added.
What is the definition of decomposition?
Decomposition is a technique used to break down the project scope and project deliverables into more managable parts.
Decomposition is used to define the project scope from the project charter by defining high-level objectives into more granular pieces.
Decomposition is used to prioritize risks into high-level catagories.
Decomposition is used to define the WBS Dictionary from the WBS.
Chris is working on the schedule for a construction project. He sees that on day 14, the concrete is being poured. However, the next step cannot start until day 21. This is known as what?
Lag
Lead
Crashing
Fast tracking
Chris is working on the schedule for a construction project. He sees that on day 30, painting can begin while the drywall is being finished. This is known as what?
Lead
Crashing
Lag
Fast tracking
The project team has developed a project schedule. However, they find out that a number of key resources will be limited during the project. What method of scheduling should they consider using to help with this?
Critical chain method
Resource leveling
Resource smoothing
Monte Carlo method
Which is the best description of the critical path.
It determines the earliest a project can finish.
The single path with no float.
It has the most number of activities.
It is comprised of the key, critical activities.
Your consulting firm has been asked to provide an estimate on Project XYZ. Recently, your company completed project RTS, which was similar to XYZ. You use RTS as a template. This is known as what?
Analogous estimating
Bottom-up estimating
Monte carlo method
Parametric estimating
Your team is working on providing the initial budget estimate of $200,000 now that the project is approved. The team is working from a previous project and are able to present a definitive budget. How much is the budget?
$200,000 with a range of -5% to +10%
$200,000
$200,000 with a range of -25% to +75%
$200,000 with a range of -20% to +30%
Tim's project team is classifying direct and indirect project costs. Which of the following is a direct cost?
Utilities for the team's office at the construction site.
Workman's compensation insurance for the team.
Utilities for the team's office in the home office.
B and C
Your team is working on a new project and will require training on the new equipment. This training is known as what?
Cost of quality
Cost of good quality
Cost of poor quality
Contingency reserves
Three point estimating has two common formulas. These are known as which?
Triangular distribution and Beta distribution
Triangular estimating and beta estimating
Most likely and pessimistic
Optimistic and pessimistic
Which of the following is a part of the budget but not the cost baseline?
Management reserves
Direct costs
Management overhead
Contingency reserves
Your team is brainstorming on the best quality tools to use on the project in creating the quality management plan. Which of the following is not a tool of this process?
Quality metrics
Statistical sampling
Cost of quality
Design of experiments
Quality initiatives such as TQM, Six Sigma and the Plan-Do-Check-Act cycle are examples of what part of quality?
Continuous improvement
Prevention over inspection
Cost of quality
Pareto diagrams
Which of the following is an input to the plan quality management process group which relies on on the organizations internal policies and practices?
Organization process assets
Templates
Requirements Documents
Enterprise environmental factors
Kevin is presenting the project quality plan to the stakeholder meeting. One of the stakeholders asks what the difference is between grade and quality. What is your best response?
Quality is the degree which the product fulfills the requirements while grade is technical characteristics of the product.
They are the same
A high grade product cannot have low quality.
A low grade product can have high quality.
Your client has been comparing your project's plan to their standards set by Six Sigma methods. This is known as what?
Benchmarking
Quality control
Standardization
Continuous improvement
There are five tools and techniques used in the plan human resources process. Which of the following is one of these?
Organizational theories
Organization process assets
Activity resource requirements
Pre-assignment
Your project will require a large multi-discipilinary team from across your company. Their functional managers require information regarding their workers and their involvement in the project. Where will this information be found?
Human resource management plan
Cost management plan and the time management plan
Work breakdown structure
Activity resource requirements
Which of the following is not an input to the plan human resources management plan?
Project staff assignments
Project management plan
Enterprise environmental factors
Organization process assets
Which of the following human resource theories states that human beings have basic needs and that people need to meet lower-level needs before they can move onto the next level of needs?
Maslow's hierarchy of needs
Ouchi theory Z
McGregor theory X and Y
Maslow's motivation theory
Your project management team is creating the human resource management plan. You are drawing up a grid that shows the project resources assigned to each of the work packages. This grid is known as what?
A Responsibility Assignment Matrix
Role descriptions
Organization chart
Tornado diagram
Carl is the project sponsor and you have been working with him on the human resources plan. Which of the following is true about the project sponsor and human resources?
The project sponsor ensures that the project manager has the necessary resources to complete the project.
The project sponsor assigns the needed human resources to the project.
The project sponsor has no role in human resource management.
The project sponsor gives the project manager authority to get specific needed resources.
Which of the following is an output of the plan communication process?
Project document updates
Work performance information
Change requests
Project communications
What is the sequence of steps in basic communication models?
Encode, transmit, decode, acknowledge, respond
Decode, transmit, encode, acknowledge, respond
Encode, transmit, decode, respond, acknowledge
Encode, respond, decode, acknowledge, transmit
Which is the most effective method to ensure a common understanding by all participants in communications?
Interactive
Push
Pull
Non verbal
The project manager is planning to have an internal team create a website for the project so that stakeholders can review the progress of the project. This is what type of communications?
Pull
Interactive
Push
This is not an appropriate form of communications for the project.
During the planning process, there are a total of 4 stakeholders. When the execution process starts, 7 more stakeholders will be added to the communications requirements. How many additional communication channels does this create?
49 additional channels
55
98
21
There are three risk themes or attitudes that can affect an organization and stakeholders. Which one of this is not considered an attitude regarding risk?
Risk register
Risk appetite
Risk tolerance
Risk threshold
What is the only output of the plan risk management process?
The risk management plan
The risk register
Risk breakdown structure
Risk probability and impact assessment
One of the inputs to the plan the risk management process is the stakeholder register. What is the best reason this is needed in planning for risks?
The stakeholder register allows the project manager to see what the roles are of each stakeholder.
The project manager can determine who is the riskiest stakeholder.
The project manager can interview the key stakeholders of risks that they are aware of.
It helps the project manager know how to identify the stakeholders who could close the project if their risks are not addressed.
Risks need to be examined for their probability, impact and either gain or cost. What term describes an organization's willingness to accept risk?
Risk appetite
Risk register
SWOT
Risk threshold
Peter is asking what a positive risk is as he says risks are all negative. You tell him what?
Positive risks are those risks where the project would benefit from an event.
Positive risks are those risks that the team know will happen.
Peter is correct, there are no risks are are positive.
Positive risks are rare and don’t normally need to be incorporated into the risk management plan.
You are managing a project that involves a new website. If you build the website, it will cost $240,000 to build and $9,000 per month to maintain. If you go to an outside vendor, it will cost $180,000 to build and $14,000 to maintain. What is your best option?
You should buy the website if it will be used less than 12 months
You should buy the website if it will be used more than 12 months
Build the website because you have more control.
Buy the website since it is more effective to give it to an outside vendor.
There are seven outputs in the plan procurement management process. Which of these is not a output?
Selected sellers
Change request
Source selection criteria
Project document updates.
The key benefit of a cost-reimbursable contract is which of the following?
They provide flexibility to redirect a seller when the scope of the project cannot be defined or there are high risks involved.
They provide stability of price for a well defined product.
They are often used for staff support or expert support when a precise statement of work cannot be written.
They can specify costs in a measurable unit such as cost per hour.
Which of the following is the most commonly used contract and most advantageous to the buyer?
Firm fixed price
Fixed price with economic price adjustment
Time and materials contract
Cost plus incentive fee
In which process groups are stakeholders identified?
Initiating, planning, executing, and monitoring and controlling.
Initiating, planning, and executing.
Initiating, planning, executing, monitoring and controlling, and closing.
Planning, executing, monitoring and controlling.
Your project team is working on a Stakeholders Engagement Assessment Matrix. The project sponsor asks what this is used for and you explain which of the following?
The Stakeholder Engagement Assessment Matrix helps determine communication gaps.
The Stakeholder Engagement Assessment Matrix helps identify new stakeholders.
The Stakeholder Engagement Assessment Matrix identifys the roles and responsibilities of the stakeholders.
The Stakeholder Engagement Assessment Matrix identifys the hierarchy of the stakeholders.
Why should precautions be taken in who receives the stakeholder management plan?
The stakeholder plan contains sensitive data on all stakeholders including those who are resistant to the project.
The stakeholder plan contains sensitive information on project financials.
The stakeholder plan may contain sensitive information regarding supportive stakeholders who may become upset if it becomes known that they support the project.
The stakeholder plan does not contain sensitive information and can be distributed freely who anyone who requests a copy.
One of the team members asks the project manager how to send out a report to the stakeholders on a certain committee. The project manager tells her to do what?
She should check the stakeholder management plan.
She should check the communications management plan as different stakeholders have different communication needs.
She should check the human resources plan for the stakeholder preferences.
Post the report on the company website so that stakeholders can access it when they want to.
Who should be in charge of the project during the executing process?
The project manager
The functional managers of the team members
The project sponsor
The key stakeholders
During the project work, the team realizes that some changes need to be made but time is short. What is the best step?
Submit the requested changes to the change control board.
By pass the change control board and begin working on them.
Submit the changes to the change control board and begin working on the changes.
Speak with the project sponsor to authorize the changes.
One of the key functions of the project manager during directing and managing the project is to do what?
Communicate
Control costs
Plan the project execution
Do the work
There are three tools in directing and managing the work. Which if these is not one of these tools?
Work performance data
Project Management Information System
Meetings
Expert judgement
A critical change has been approved by the change control process. It will become an input which process?
Direct and manage project work
Validate the scope
Perform integrated change control
Monitor and control project work
All of the following are part of the direct and manage project work process except?
Create the WBS
Using the WBS
Meetings
Project management plan updates
You are in the middle of the project when you discover that two key materials will not be available as planned. Your best course of action is to do what?
Set up a meeting with the project sponsor to discuss the impact and possible workarounds.
Set up a meeting with the sponsor to complain about the lack of materials.
Crash the project
Present fast tracking the project to the project sponsor.
You are approached by a key stakeholder who offers you a promotion if you delay the project by a few days. What is your best response?
Inform him that you are unable to do that.
Submit the request as a change request.
Report the key stakeholder to PMI.
Review the project schedule to see if the project can be delayed.
One of your key stakeholders has requested a delay in a project task in order to focus on a project unrelated to yours. You know that this will not affect the critical path. What is the best response
Submit the requested changes to the change control board.
Add a lag to that task.
Inform the stakeholder that you are unable to take this kind of action.
Crash the project to make up for the delay.
The team wants to update the schedule with some key changes. What is the best course of action for this task?
Submit the requested changes to the change control board.
Make the changes since you are not affecting the project deliverables.
These documents do not need to be changed.
These changes need to go to the project sponsor first before making them.
Due to severe quality problems, the project sponsor has told the project manager that quality is the most important issue now. If a problem occurs with quality, what is the best course of action?
Permit the cost to increase to correct the root cause of the problem.
Fix the defective parts immediately.
Modify the risk management plan to account for the increased quality issues.
Increase inspections on the parts.
The project is implementing a new quality system and the quality department is doing its own investigation of this new system. What action does this department take to make sure the new system is working?
Perform a quality audit
Perform control quality
Process improvement
Perform quality metrics
You are currently working on quality audits for the project. What process group are you in?
Perform quality assurance
Plan quality management
Control quality
Executing process group
The team is meeting regarding a new feature that another part of the company is using. This feature is not referenced in the project scope. What is this known as?
Gold plating
Continuous process improvements.
Scope creep
Versioning
The project manager informs the team that they need to plan how to implement the quality policy. If this plan changes, which plan will also have to change?
Quality management plan
Quality control plan
Risk management plan
Project management plan
Your team has been told that they will be audited by an outside quality management firm and they are concerned. What do you tell them?
Quality audits are to look for inefficiencies in the company's policies.
Quality audits are a part of a proposed ISO 9000 program.
The customer wants to know what the company's policies are.
Check that the project costs are accurate.
The project has a CPI of .9 and an SPI of .92 when a key stakeholder asks you about some concerns she has on the quality of the project standards. What should you do in this situation?
Put a quality assurance team to review the project and the quality standards to demonstrate that the project is meeting the quality standards.
Assure the stakeholder that the project is progressing as expected and show them the CPI and SPI as proof.
Assure the stakeholder that the project quality plan is being followed.
Review the previous project to determine if your project is following the same quality assurance program.
You are performing quality assurance and selecting tools and techniques to implement this. Which of the following will not help you?
Brainstorming
Affinity diagrams
Quality audit
Process analysis
The team is preparing for a quality assurance audit and they are gathering the materials for this. What do they need?
Quality control measurements
Change requests
Deliverables
Quality audit
Which quality assurance tool follows the process improvement plan to identify needed improvements?
Process analysis
Quality audit
Quality management and control tools
Design of experiments
You are meeting with the human resources department about acquiring the project team. What process group are you in?
Executing process group
Initiating process group
Planning process group
Human resource management.
The new project manager was promoted from senior developer. He was considered one of the best developers but is not doing well at managing his first project. His promotion was due to what?
Halo effect
Maslow's hierarchy of needs
Deming cycle
Leadership
There is a minor conflict between two team members. They ask the project manager to help them resolve the issue. However, the project manager says that he is unable to work with them as he is working on a critical problem with the client. This conflict resolution technique is known as what?
Withdrawing
Forcing
Compromising
Smoothing
You and your assistant are working on a chart to present to management about the allocation of resources during the first two months of a four month project. What is the best tool to do this?
Resource histogram
Project organization charts
RACI Matrix
Schedule management plan
You are in charge of a small team working with others on a large project. Another team has missed several deadlines which your team depends on. You have spoken to the manager of the other team several times yet they have missed another deadline and your team will have to work through the weekend. What is your best course of action?
Speak with the project manager and the leader of the other team.
Speak with the project manager.
Speak with the team leader again.
Speak with the PMO office.
The team is discussing who should take responsibility for each WBS when a couple of team members disagree about some of the work packages. One member says that one work package needs to be decomposed further, while another says that another work package should be put in a different category. Your best option is to do which of the following?
Focus the team with a brainstorming session to get multiple possible solutions and then work with the team to select one.
Stop the meeting and have one on one meetings and then pick a solution.
Try to find some common ground and to keep the team focused on the work.
Try to find what options everyone will be comfortable with.
The project you have been managing has been hard with a large number of approved changes. The team has been struggling to keep up and meetings are uncivil. Two team members will only attend by webcam and the rest of the team gets upset over the latest change. What is the best step to take?
Set up new ground rules for meetings.
Arrange a team building exercise.
Make the team a virtual team.
Invite a company mediator to sit in on the meetings.
You are into the third phase of a project and your core project team will be taking on four new members. What stage of the Tuckman ladder will they be on when they start this phase?
Forming
Norming
Performing
Adjourning
The PMO has made you the project manager after the previous manager left for a new position. Your project has completed a work package and two members of your team are not needed after this. Where should you get the information on how to release them?
Review the human resource management plan from the PMO
You cannot release them on your own. You need your team to release them.
Call the previous project manager.
Call their functional managers and tell them they have been released.
The project will involve far more communication than your team has been used to in previous projects. What is the best way to ensure the best communication with all stakeholders throughout the project?
Enroll the team in a communications seminar
Assign one member of the team as head of communications.
Hire a communications firm to handle all communications.
Review the communications management plan
There are a number of complicated issues that will need to be communicated. What is the best way to handle this?
Formal and written
Informal and written
Informal and verbal
Formal and verbal
Regularly scheduled meetings are important for consistent updates. Which of the following is not a part of performance reporting?
Stakeholder register
Work completed
Summary of approved changes
Status reports
During a conference call, one member has had his microphone on while talking to people in the hallway. What might this noise result in when it comes to the project team?
Increased conflicts
Increased trust
The project manager gets upset.
Increased costs
One example of a situation that requires formal written correspondence?
The client requests additional changes that are not within the contract.
The project has some minor overruns.
A couple of steps on a non-critical path are delayed.
The client has additional changes within the contract.
You are taking over a project that has been going on for the last 6 months. You have to assess the project quickly for your first meeting with the project team. What document should you request first?
The latest progress report
The communications plan
The complete progress report.
Stakeholder register
An important change to the deliverables has been approved. All the stakeholders have been notified according to the communication management plan. A week later, a stakeholder calls and asks when this change was approved as it will affect some of his work. After informing the stakeholder of the timing of the change, what is the next best thing to do?
Review the communication plan and make any revisions.
Send out an email to all stakeholders about the change.
Post the change on the project website for all stakeholders to check for changes to the project.
During the next meeting with the PMO, revise all company communication plans.
The project team is going to be adding 3 new team members to the group of 6 not including yourself as the project manager. How many total lines of communication will there be?
45
90
36
72
The virtual project team consists of people located in the seven different countries. What will be the the most critical tools for a successful project?
Well defined communications and people skills
Videoconferencing equipment
Research on cultural differences
Good translators
The computer upgrade project you are managing is very complex and was difficult to get approval. A lot of stakeholders wanted everything customized for their department but this was not possible. As you are now four months into the project, change requests are starting to come in. What will not help you in rejecting change requests for items refused during the project initiation?
Emails with the stakeholders to review all rejected requests to remind them not to request it again.
Maintain issue log
A list of rejected requirements for review in the change control process.
Maintain a detailed list of rejected changes and why they were rejected.
The project manager is asking for a report which shows actual results versus planned results. Which report will provide this information?
Variance report
Progress report
Status report
Risk report
You are gathering information for a regular update on the project for the stakeholders. What will you not need?
Project information management system
Communication management plan
Work performance reports
Organization process assets
You are writing the regular project document updates for the project. What tool would not be useful?
Project communications
Performance reporting
Information Management Systems
Communications technology
What are the main reasons for the conduct procurement process? C128
Obtain seller responses, select a seller and award a contract.
Document project decisions, specify the approach and identify potential sellers.
Completing each procurement and performing the necessary administrative tasks.
Maintaining procurement relationships, verify contract performance, and make necessary changes to contracts.
You are reviewing the procurement documents to make sure they include all of the following except?
They should be rigid and restrict outside suggestions.
They should include the selection criteria.
They should include the statement of work.
They should follow the buying organization's format and any other regulations.
You are going to be negotiating the contracts in the next few days. What is your main objective with the negotiations with the seller?
Creating and maintaining a relationship so that the project suceeds.
Getting the lowest price so the project is under budget.
Make sure that the seller agrees to all of the details of the contract.
Getting each seller to compete for the business so you get the best terms.
Your organization requires that you obtain three estimates from outside professional organizations and one from the PMO before starting negotiations. This technique is known as what?
Independent estimates
Expert judgement
Bidder conference
Proposal evaluation techniques
While negotiations are important for the project manager, what is the best statement regarding a project manager's role in negotiations?
The project manager should be available to provide assistance and any needed information.
Take the lead
The project manager should let the organizations purchasing department handle all negotiations.
The project manager needs to review all procurement documents to make sure they meet all the legal requirements.
Your team is reviewing the different proposals that have been submitting for some work that needs to be contracted out. What process group is your team in?
Conduct procurement
Control procurement
Close procurements
Plan procurement
Your project is behind schedule and the decision to contract out some of the work has been made. In the past you have worked with ABC Contractors on smaller projects and want to use them. What should be a concern?
ABC Contractors qualifications
Selection criteria
Bidder conference
Make or buy decision
The proposals from the various sellers are in and your purchasing committee is reviewing the bids according to the weighted criteria in the procurement management plan. They are doing which of the following?
Proposal evaluation techniques
Bidder conference
Advertising
Analytical techniques
As part of your proposal, you need to submit the credentials of an engineering team to be permitted to bid on the project. This type of requrement is known as what?
Screening system
Project requirement
Statement of work
Source selection criteria
Your organization wants to train a group of people for the PMP exam. There are a number of qualified training companies in the area, but your organization prefers to work with the closest company. This is an example of what?
Single source
Sole source
Illegal selection
Qualified vendor list
The team wants to know why they need to maintain communications with the stakeholders all the way through the project. What is the key benefit of stakeholder engagement?
It allows the project manager to increase support and decrease resistance in order to achieve success.
It maintains the effectiveness of stakeholder engagement activities.
It enables clear and effective communications between the stakeholders.
It maintains the stakeholder register.
Which two management plans do you need to manage the stakeholders?
The stakeholder management plan and the communication management plan
The stakeholder management plan and the project management plan
The stakeholder management plan and the procurement management plan
The stakeholder engagement plan and the communications plan
The project is nearing completion but there is one last milestone to reach. The initial excitement of the stakeholders is long gone and you need to keep them involved. What would be the best way to do this?
Have the stakeholders review the requirements that remain to be met.
Invite them to the kick off meeting.
Invite them to the weekly status meetings.
Send the latest approved changes to them.
Your time will be limited to spend with the stakeholders. Which stakeholder would be most important to work with?
The head of the department that will be using the product. He is not actively engaged in the project.
The lead designer of the project who is enthusiastic about it.
One of the users of the product who is resistant to it.
The project sponsor who you have worked with on the last three projects.
After having a meeting with a number of internal stakeholders, the project assistant needs to update the lessons learned and note what the stakeholder feedback was. These are examples of which stakeholder management output?
Organizational process asset updates
Project documents updates
Issue log
Change requests
Your project is on budget and on schedule. Your team has come up with a demo for the sales team to use for making their presentations to prospective customers. You will do which of the following at the next stakeholder project status meeting?
Report on the progress of the demo and inform them that it is complete.
Give the stakeholders a preview of the demo and have them sign-off to approve it. +Review all of the sales material that will go with the demo.
Report that the demo is complete and has been updated in the PMIS.
For a project lasting 12 months, how often should the stakeholder management plan be reviewed during the execution of the project?
It should be reviewed on a regular basis but determined by the project manager
Never, once the stakeholder management plan is complete, it does not needt to be updated.
Once a month
Once a week
During a meeting between the key stakeholders and key team members a dispute has come up as how to handle a technical issue. What type of skills does the project manager need to use most to get the group to come to a consensus?
Management skills
Interpersonal skills
Communication methods
Analytical techniques
There is a resistant stakeholder who is key to the project success. Which set of skills would the project manager need to use to change their outlook on the project?
Interpersonal skills
Management skills
Stakeholder notification
Expert judgement
After a meeting with the financial department, there have been some changes to the amount of money available for the project. What will need to be updated in the manage stakeholder process?
Project management plan updates
Change requests
Issue log
Organization process assets
Your team is working on Friday morning for the afternoon updates to the internal stakeholder meeting. Most of their work is about the progress made this week and the forecasts for next week. What process group are they working on?
Monitor and control project work
Integrated change control
Validate scope
Cost control
What important cost and schedule forecast calculations are important in monitor and control project work?
Cost variance and Schedule Performance Index
Actual cost and budget at completion
Planned value and Earned value
To-Complete Performance Index
A project team is writing up a number of updates and reports to complete the monitor and control project work process. What will they not produce?
Approved change requests
Change requests
Work performance reports
Project document updates
The project manager needs to be aware of changes. In addition, the project manager should also do what?
Prevent unnecessary changes
Tracking and recording changes
Informing the CFO of changes
Add changes to the lessons learned
During quality control, the project team found a problem and submitting a change to use a different grade of materials. This change does not impact the scope, cost or schedule. The change control board has approved the change and the project manager is updating various documents. What document needs to be updated?
Configuration control documents
Scope baseline
Organizational process assets
Stakeholder register
In the monthly financial report, you see the following information: CPI =1.1, SPI=.9, PV=$500, SV=-$200. You cannot find the CV so you need to calculate it. What is the CV?
$41
$409
$450
$300
Your project has an initial budget of $100,000. A couple of months into the project you perform a budget analysis. You should have spent $50,000 and 100 hours on the project. Upon review, you discover that $60,000 has been spent and that 110 hours have been completed which should have cost $45,000. You reevaluate the remaining work to be done and your new budget is $120,000. What is the CPI and SPI?
CPI = .75, SPI = 1.1
CPI = 1.1, SPI=.75
CPI = .83, SPI = 1.1
CPI = 1.1, SPI = .83
Your project has an initial budget of $100,000. A couple of months into the project you perform a budget analysis. You should have spent $50,000 and 100 hours on the project. Upon review, you discover that $60,000 has been spent and that 110 hours have been completed which should have cost $45,000. You reevaluate the remaining work to be done and your new budget is $120,000. What is the CV and SV?
CV = -$15,000, SV = 10
CV = $15,000, SV = 10
CV = $60,000, SV = 100
CV = $15,000, SV = -10
Your project has an initial budget of $100,000. A couple of months into the project you perform a budget analysis. You should have spent $50,000 and 100 hours on the project. Upon review, you discover that $60,000 has been spent and that 110 hours have been completed which should have cost $45,000. You reevaluate the remaining work to be done and your new budget is $120,000. What are the conditions of the project?
The project is over budget, ahead of the schedule, and more expensive than originally planned.
The project is over budget, behind schedule, and more expensive than originally planned.
The project is under budget, behind schedule and more expensive than originally planned.
The project is on budget, on schedule, and less expensive than originally planned.
Your project has an initial budget of $100,000. A couple of months into the project you perform a budget analysis. You should have spent $50,000 and 100 hours on the project. Upon review, you discover that $60,000 has been spent and that 110 hours have been completed which should have cost $45,000. You reevaluate the remaining work to be done and your new budget is $120,000. What baselines must be changed?
Cost baseline
Scope baseline
Schedule baseline
Cost and schedule baselines
Your project has an initial budget of $100,000. A couple of months into the project you perform a budget analysis. You should have spent $50,000 and 100 hours on the project. Upon review, you discover that $60,000 has been spent and that 110 hours have been completed which should have cost $45,000. You reevaluate the remaining work to be done and your new budget is $120,000. What should be the next step?
Request a change to the budget.
Use the contingency funds set aside for this.
Request additional funding from the sponsor.
Crash the project
The key tool in controlling the scope of a project is variance analysis. What is the best definition of this?
Determining the cause and degree of difference between the baseline and the actual performance relative to the scope baseline.
The difference between the EV and AC.
The difference between earned value and planned value.
This determines the underlying causes of a difference between the actual results and the planned results.
The project manager announces to the team that the deliverables are now accepted. What is the best explanation for this?
The customer has formally signed off and approved the deliverables.
The customer has verified that the deliverables meet the acceptance criteria.
The quality control team has formally signed off and approved the deliverables.
The quality control team has inspected the deliverables and they are ready for acceptance.
The quality control team and the scope validation group, which includes a team member of the client, are working on control quality and scope validation at the same time. A team member objects to this stating that they are two different processes. What is the next best course of action?
Performing both in parallel is a reasonable practice.
The scope validation team should wait until all the deliverables have passed the quality control team.
The quality control team should wait until the deliverables have passed the scope validation team.
There is no need for a client member on the scope validation team.
Your team is nearing completion of the project when the client is purchased by another company. As a result, the project has been cancelled. What should be done about scope validation?
The scope should be validated up to the point of the cancellation.
Store all deliverables for another project as lessons learned.
Nothing needs to be done because the project is cancelled.
The project is deemed a failure and the deliverables are scrapped.
How often may scope validation occur?
Multiple times
Once at the end of the project.
Each time the deliverables are verified.
When the customer asks for them.
You have reviewed the latest SPI and want to fast track two activities. There is minimal risk and getting these two activities done will give you an opportunity to give the team a day of light work next week. You prepare a change request to make this happen. What process group are you working in?
Control schedule
Control risk
Manage human resources
Control cost
The software portion of the project is running a couple days behind schedule. It is not on the critical path. The initial resource was supposed to be a senior developer, but he was not available. He has now become available. What is the best course of action?
Arrange a proper handover from the person working on it now to the senior developer.
Crash the project
Fast track other activities
Submit a change request to change the schedule.
At the end of the first month of a six month project, the project manager is reanalyzing the schedule. She is putting together a sequence of activities with the least amount of scheduling flexibility. What is this called?
Critical path method
Flow charting
Work breakdown structure
Decomposition
The project team is having their retrospective review and determining the current velocity. What type of approach are they using?
Agile
Waterfall
PRINCE2
These are not PMI terms.
Scheduling tools include network diagrams for illustrating activities. However, bar charts are used best for which illustrations?
Progress or status
Critical path
Correlation between two variables.
Logical relationships
The project manager is reviewing a schedule diagram and removes a step required to complete another task. She then changes that task to include the activities for the previous task. What should she do next?
Mark these changes as a proposal and submit a change request.
Submit a change request.
Direct and manage the work.
Update the risk register
Your team is reviewing a graph which shows a bar chart listing the most recent quality problems and their frequency. You are in what process group?
Control quality
Plan quality
Scope management
Control risk
There are a total of eight inputs to control quality. Which of the following is not an input?
Enterprise environmental factors
Organizational process assets
Quality checklists
Deliverables
The project team has a quality standard of 3 sigma. What is the percentage that is represented by this number?
99.73%
99.9997%
69%
0%
The team completed reviewing the deliverables and needs to use one additional tool. Which of the following tools are used in quality control?
Approved change requests review
Design of experiments
Risk audit
Quality metrics
The quality standard for the parts needs to be 4 inches. A sample of parts is 4.33, 4.29, 4.34, 4.31 and 4.30. What can be said about the parts?
They are precise but not accurate
They are accurate and precise.
They are not accurate nor precise.
They are accurate but not precise.
Controlling communications ensures that the information needs of the stakeholders is met. What is not a tool of control communications?
Change requests
Information management systems
Expert judgment
Meetings
You get an urgent call from a manager on the electrical portion of the project. He has not received a progress report for the last two weeks. You email him a copy right away but what should you do next?
Check the email that you used and compare it to the communications plan.
Submit a change request.
Update organizational process assets.
Update project documents.
A manager in your project has changed and the new person is requesting a progress report. Which tool should you direct your staff to use to provide this for him?
Information management system
Change request
Organizational process assets
Communications management plan
The project had a major problem and your team is now in crisis. What should be done with communicating the problem?
Review the communications management plan.
Alert all stakeholders.
Tell only the project sponsor.
Review the stakeholder register.
The issue log is an input to control communications. What is it used for in this process?
It provides a repository for what has happened and a platform for communications that are to be delivered.
It provides a repository for what has happened.
It provides a platform for communications that are to be delivered to stakeholders.
It provides information to document and monitor the resolution of issues.
What is the best definition of contingency plans and workarounds?
Recommended corrective actions
Recommended preventative actions
Change requests
Risk controls
Valerie has been comparing the last six weeks of performance data. She notices that everything is still within specifications but that the data appears to be going up a couple percentage points each week. She is involved in what activity?
Variance and trend analysis
Reserve analysis
Risk audit
Risk reassessment
During the weekly risk management meeting, your team is reviewing a high risk situation. They realize that the original response will not work as planned if the risk occurs. What should the next step be?
Plan a new response.
Submit a change request.
Engage stakeholders
Change the risk register.
A previously identified risk has occurred. However, the risk response was not adequate to correct the problem and another $1,000 is needed to correct it. What can the team not do?
Use the contingency reserves set aside for another risk that has not occurred.
Submit a change request for additional funding.
Develop an additional response to the issue.
Review other parts of the budget for savings to cover the problem.
Most risks will be identified during which process?
Identify risks and control risks
Identify risks
Identify risks and risk audits
Identify risks and perform qualitative risk analysis.
The project is running overbudget and the project sponsor has asked you to see if you can negotiate with one of the vendors about their cost. You talk to the vendor and they offer to cut their bill by 10% if you make them the preferred vendor for a bid for another project. Your best course of action is which of the following?
Set up a meeting with the project sponsor and the PMO about the offer.
Refuse as this violates your ethics.
Agree and submit a change request.
Submit a change request and talk to the senior management about the vendors request.
Your project team is reviewing the work completed so far by a key vendor. The vendor's project manager has brought in documentation on lessons learned so far in order to identify key performance indicators. What is the activity you are currently performing?
Procurement performance review
Inspection and audit
Claims administrator
Change requests
Your quality team is not satisfied with the work of the vendor and has rejected the deliverables. You need to do which of the following with the seller?
Request that they rework the parts to the desired tolerances.
Submit a change request.
Terminate the contract.
Close contract and write a new contract to perform the rework.
During contract negotiations, Jim makes some detailed notes which Sally signs. The contract is signed. However, while the work is being performed, Sally says she does not have to do the work in the notes because those were not included in the contract. What is required for Sally to do?
Sally only needs to do what is in the contract.
Sally needs to do all of the work in the notes.
The contract should be rewritten and signed by both Jim and Sally.
The contract is voided.
The control procurements process is tied closely to other monitor and control processes. Which process is the contract change control system integrated with?
Integrated change control
Direct and manage work
Control risks
Control quality
The building has passed the final fire inspection. What should the next step be?
Update the stakeholder register and mark the fire warden as no longer involved.
Update the stakeholder register and add the fire warden.
Update the human resource management plan and remove the fire warden.
Update the procurements documents and close out the contract.
During a meeting with the project management team, the project sponsor mentions that he has to focus on a higher priority project. Your project is running smoothly but you still need some support. Your strategy should be to do what with the sponsor?
Keep them satisfied
Manage closely
Monitor
Keep informed
One of your senior managers sends you an email to address an upcoming concern. It says that a key stakeholder always expresses doubts when a certain milestone is in question. What is your best action to address this?
Update the stakeholder register and review some strategies to address this potential issue.
Wait until the stakeholder brings up their concern.
Wait until the stakeholder brings up their concern.
Update the stakeholder register with the warning but wait until the stakeholder raises this concern.
A team member notices that there is a variance between the performance measurement and the planned performance. She notifies the project manager. The project manager reviews the scope document and discovers that this measurement was not identified in the planning process. What project management process is this event a part of?
Monitor and control
Executing
Planning
Initiation
The team is reviewing the requirements tractability matrix while validating the scope. What is this used for?
This links the various requirements to their origin and tracks them through the project.
This links the team members to the individual requirements and tracks who is responsible for them.
This links the project resources to each work package.
This links the requirements to the assigned stakeholders and which stakeholders are requesting the requirements.
Which of the following tools is the primary method to adjust the start times of a successor activity without work or resource impact?
Leads and lags
Fast tracking
Crashing
Resource leveling
There has been a change to the cost baseline. What portion of the budget does not necessarily change?
Management reserve
Contingency reserve
Active contingency reserve
Activity costs
When are risk responses implemented?
Control risks
Direct and manage project work
Monitor and control process group
Plan risk responses
The final deliverables have been accepted by the internal department. What is not a tool of project closure?
Benchmarking
Meetings
Expert judgement
Analytical techniques
The phase has now been ended and what happens to the deliverables that were accepted?
These deliverables can be used in the next phase.
Since the phase is over, the deliverables are not needed.
Since the project is over the deliverables are used in production.
The deliverables need to be validated first.
As the team works on closing out the phase, a new intern asks what are the main benefits of a formal closing when all of the work has been done. What is not a key benefit of closing the project?
The deliverables are accepted.
Provides lessons learned for the project.
Formal end of the work
Release of organizational resources
What is not needed as an input to the close project process?
Scope management plan
Project management plan
Accepted deliverables
Organizational process assets
The company is being bought out and the project that was just started has been terminated. What should the next step be by the project manager?
Begin the close project process.
Review the project charter as the details for the buyout are contained there.
Review the project management plan for closing the project.
Begin filing all of the documents as part of lessons learned.
During the close project process, one other process is closed out at the same time. Which of the following is closed out as well?
Close procurements
Close scope management
Releasing the resources
Close the budget
Which of the following is not updated in organizational process assets during the project closing?
PIMS
Project files
Project closure documents
Historical information
The buyer has completed the purchase and Sue is putting the final documents into the closed procurements file. These include the procurement file, lessons learned and the formal acceptance letter. These are part of which of the following?
Organizational process assets updates
Procurement audits
Enterprise environmental factors
Procurement documents
Your team reviewed a significant task and decided the best course of action was to outsource the work. Your SPI is .9 and you are finalizing the open claims with the vendor. What process are you working in?
Closing procurements
Close project
Validate scope
Control procurements
Due to a change in the market conditions, a project is being closed and the procurements that are being conducted also need to be closed. In which process group are the details to manage early terminations be found?
Control procurements
Close procurements
Plan procurements
Manage procurements
The project team have had a number of problems with the vendor and it has been decided and supported by senior management to terminate the contract. The vendor is demanding full payment but the deliverables were not completed. What is the next best action?
Hire a mediator to help resolve the issue.
Get the legal team to begin a lawsuit.
Have the vendor finish the contract and then never work with them again.
Begin contracting the rest of the work with another vendor.
There are two processes involved in the closing process group. Which of the following statements is true?
The close procurements can happen multiple times.
The close procurements occurs only once.
The close project process can happen multiple times.
Close scope only happens once.
While closing out a particularly complex set of procurements, the project manager asks the author of the contract to help him with reviewing the procurement process to identify success and failures. This is known as what?
Procurement audit
Procurement negotiations
Procurement closure
Control procurements
{"name":"Final Exam 2", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"The most important output of Define Scope is, You and the project sponsor are developing requirements for an internal project. The charter will include all except the following?, You are defining the initial scope of a new project as for an external customer. All of the following are items that you will use for the initial inputs except?","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}
More Quizzes
¿Que profesor del colegio serias?
840
Nouns
210
American Republic Study Quiz
26130
Quiz: Are These Donald Trump Quotes or Grime lyrics?
30150
Neuro 6
15810
Webdam feedback
210
STRUCTURE QUIZ - Session 4
10524
Cat de bine il cunosti pe Calin Barbarul? :D
116221
Do you have any recommendations in new papers today?
100
320
ZBT AWARDS 2018
41200
Animal quiz
630