6 HR Quiz

Acquire Project Team, Develop Project Team and Manage Project Team are all contained within the following Process Group?
Executing
Cannot be determined
Human Resources Management
Direct and Manage Project Work
All of the following are outputs of 'Acquire Project Team' process Except?
Project Team performance assessments
Project staff assignments
Resource calendars
Project management plan updates
Andrea is nearing the end of her project. There are still some final deliverables to complete and she is reviewing the human resource management plan. She reviews the completed appraisals  for each member of the project team. She prepares the awards and performance bonuses for the team leaders. What process group is she working in?
Develop project team 
Close project 
Manage project team 
Acquire project team 
In the Tuckman ladder model, the stage where the teams learn to trust each other is:
Norming
Storming
Adjourning
Forming
In which phase of the Tuckman model does the team work as a well-functioning unit?
Performing
Adjourning
Contributing
Norming
Phil is trying to resolve a dispute between two divisions of the software development teams. This is a part of which process?
Manage project team
Develop project team
Acquire project team
Manage stakeholders
Rich is the project manager for a multinational corporation and working with a virtual team dispersed across the United States, Brazil, Egypt and Japan.  The communications plan intends to use video and teleconferencing when team members need to communicate with each other.  The benefits of this arrangement include all except the following:
Make use of local human resource policies
Add members to the project team regardless of location
Form teams with resource who work different shifts
Reduce travel expenses
The project manager is working with the head of the HR department. What is the most useful paperwork that the project manager should bring to help in selecting the team? 
Activity resources requirements 
Organizational chart 
Cost control activities 
WBS 
The project team has been selected to work on a project similar to the project they just completed. Which phase of the Tuckman ladder is the team most likely to pass through quickly?
Storming 
Norming 
Performing 
Adjourning 
The project team has run into a major problem and are waiting for the quality control results to evaluate the situation. However, team members are bickering amongst themselves and placing blame on the manager who was in charge of risk management. The project manager needs to resolve the situation temporarily by which conflict management method?
Withdraw/ avoid 
Smooth / accommodate 
Force / direct 
Collaborate / problem solve 
{"name":"6 HR Quiz", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Acquire Project Team, Develop Project Team and Manage Project Team are all contained within the following Process Group?, All of the following are outputs of 'Acquire Project Team' process Except?, Andrea is nearing the end of her project. There are still some final deliverables to complete and she is reviewing the human resource management plan. She reviews the completed appraisals  for each member of the project team. She prepares the awards and performance bonuses for the team leaders. What process group is she working in?","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}
Powered by: Quiz Maker