3 Time Quiz

Which of the following is NOT a technique used in the estimate activity resource process?
Decomposition
Project management software
Published estimating data
Expert judgment
The schedule management plan is an input to all of the following processes EXCEPT?
Control schedule
Define activities
Estimate activity resources
Develop schedule
A key stakeholder is asking why the initial plan is only detailed out for the first month, while the next three months are only loosely defined and the final three months are just a list. You explain that this technique is what?
Rolling wave planning
Decomposition
Analytical techniques
PDM
You are a project manager working for a pharmaceutical firm and the project you have undertaken is very critical for the client's business. Your development team is diligent and performs the tasks with a high degree of quality. You generate periodic performance reports and share it with upper management and they are happy with the progress of the project. Due to a business constraint, the client calls you in and explains that the project needs to go 'Live' a full two months earlier than it was originally scheduled to in order to help them remain competitive in the market. As a project manager, which of the following is the BEST thing to do to complete the project according to the new schedule?
Meet with the development team and explore options of schedule compression on the critical path
Report the conversation you had with the client to your supervisor
Inform upper management that the activities of the project are on critical path and the project cannot be finished faster
Inform the client that the initial agreed date of project delivery cannot be changed
A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of which of the following? 
Finish-to-Start 
Start-to-Finish 
Start-to-Start 
Finish-to-Finish 
The printing project is running two days behind schedule and in order to catch up, the team has agreed that editing the document can start a day earlier than planned.  This is adjusting which of the following?
Lag time
Crashing
Compressing the schedule
Fast tracking
The construction project is not going well and the project manager has reevaluated the current schedule.  She realizes that with the current plan, the building will be very behind on the schedule. Her best approach to resolving the issue is to do what? 
Develop a list of options and to present to management and recommend the best one. 
Call for a stakeholders meeting and let them know of the problem. 
Hire additional labor and work overtime. 
Cut the product scope by eliminating the upgrades. 
The project manager is reviewing the project management plan, the work performance data, and the project schedule. She is getting ready to do which of the following?
Schedule control
Plan the project schedule.
Create the WBS
Work the project plan
The process that generates the activity list is:
Define Activities
Create WBS
Plan Risk Management
Sequence Activities
The largest knowledge are in the PMBOK is:
Time
Scope
Cost
Quality
{"name":"3 Time Quiz", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Which of the following is NOT a technique used in the estimate activity resource process, The Risk management plan is an input to all of the following processes EXCEPT, Decomposition is a tool and technique of which two Project Management Processes?","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}