2 Scope Quiz

As the PM you have been very busy directing and managing project work and you have finally completed all of the major deliverables that were documented in the requirements documentation. The requirements documentation is something that is created in which knowledge area?
Project Scope Management
Collect Requirements
Develop Project Charter
Integration Time Management
Control scope process contains all of the following as Inputs except:
Verified deliverables
Project management plan
Requirements documentation
Work performance data
Decomposition is a tool and technique of which two Project Management Processes?
Create WBS and Define Activities
Develop Project Charter and Identify Stakeholders
Perform Quality Assurance and Control Quality
Define Scope and Collect Requirements
Inspection is a technique used in the 'Validate Scope' process. The main purpose of using this technique in this process is to deal with
Acceptance of the deliverables
Quality of the deliverables
Testing of the deliverables
Correctness of the deliverables
Which information in the scope baseline is used as an input in Plan Quality Management?
Project scope statement within Scope baseline provides definition of acceptance criteria, which may influences increase or decrease quality costs and project costs.
Scope baseline provides detailed information on WBS elements
Scope baseline documents the accepted time interval being used to measure cost performance
Scope baseline provides schedule performance measurements including Start and finish dates
Which of the following is NOT an input in to the 'Control Scope' process
Verified deliverables
Requirements documentation
Project management plan
Work performance data
While working on the Work Breakdown Structure for your project, you need to identify detailed assumptions and constraints that were worked on earlier in the planning and initiation process. There are a number of sources that contain information pertaining to these, but which will be the best source for the WBS?
Project scope statement
Scope management plan
Project charter
Project statement of work
You are currently working on validating the scope on your project. Which of the following will you be doing?
Reviewing the performance of an installed software module with the customer
Checking with your internal group that the deliverables meet quality control
Auditing the quality control process
Reviewing the requested changes to the scope of the product
You are the project manager at a local hospital and currently overseeing the installation of new computers. A primary responsibility is dealing with the change request process. During which process does the project manager prevent scope creep?
Control Scope
Validate Scope
Define Scope
Perform Integrated Change Control
All of the following are examples of 'group creativity techniques' EXCEPT
Mind mapping
Multi-criteria decision analysis
Affinity diagram
Observations
{"name":"2 Scope Quiz", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"As the PM you have been very busy directing and managing project work and you have finally completed all of the major deliverables that were documented in the requirements documentation. The requirements documentation is something that is created in which knowledge area?, Control scope process contains all of the following as Inputs except:, Decomposition is a tool and technique of which two Project Management Processes?","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}