DPWH Project Scheduling Quiz

Test your knowledge on the Department of Public Works and Highways (DPWH) project scheduling techniques, specifically focusing on the Precedence Diagram Method (PDM). This quiz covers important Department Orders, standard project durations, and critical path concepts.

  • 10 multiple-choice questions
  • Assess your understanding of DPWH guidelines
  • Score your knowledge and learn more!
10 Questions2 MinutesCreated by PlanningPro202
The adoption of Precedence Diagram Method (PDM) as a project scheduling techniques for DPWH projects is required under what Department Order?
A) DO 100 S. 2015
B) DO 159 S. 2015
C) DO 44 S. 2012
D) DO 133 S. 2015
All DEOs implemented projects shall adopt the Precedence Diagram Method (PDM) as a construction schedule starting _____.
A) July 1, 2016
B) January 4, 2016
C) June 30, 2017
D) January 2, 2017
It is a network diagram that shows activities as nodes and usually represented by rectangular/square boxes which are connected by arrows showing relationship between the work activities.
A) PERT/CPM
B) Precedence Diagram Method (PDM)
C) Critical Path
D) Gantt Chart
It is the longest sequence of activities in a construction schedule from commencement to completion wherein the sum of the activities duration is equivalent to the duration of the project.
A) Critical Activities
B) Parallel Activities
C) Critical Path
D) Construction Activities
The standardization of Project Duration for Standard DPWH is required under what Department Order?
A) DO 44 S. 2012
B) DO 159 S. 2015
C) DO 100 S. 2015
D) DO 133 S. 2015
It is the difference between scheduled and actual accomplishment per approved construction schedule that is usually indicated in percentage.
A) Percent time elapsed
B) Slippage
C) Negative Slippage
D) Positive slippage
What is the standard project duration of a Standard Two (2) Storey 4-classroom DPWH School Building project prescribed under D.O. 159 series of 2015.
A) 115 C.D.
B) 120 C.D.
C) 140 C.D.
D) 150 C.D.
What is the standard project duration of a Standard Four (4) Storey 20-classroom DPWH School Building project prescribed under D.O. 159 series of 2015
A) 180 C.D.
B) 195 C.D.
C) 225 C.D.
D) 240 C.D.
The significance of the item/activity along the critical path of the PERT/CPM Network Diagram are the following except ___.
A) The duration’s summation becomes the contract time.
B) It defines the shortest possible time to complete the project
C) One hour delay in any of the items will mean the whole project will be delayed by an hour.
D) It defines the critical and non-critical activities to complete the project
Approved Construction schedule, Bar Chart and S-curve are documentary requirements for _________.
A) POW and ABC approval
B) Contract processing and approval
C) Contractor’s bid proposal
D) Request of Advance Payment
{"name":"Additional Scheduling Questions", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Test your knowledge on the Department of Public Works and Highways (DPWH) project scheduling techniques, specifically focusing on the Precedence Diagram Method (PDM). This quiz covers important Department Orders, standard project durations, and critical path concepts.10 multiple-choice questionsAssess your understanding of DPWH guidelinesScore your knowledge and learn more!","img":"https:/images/course1.png"}