C-10

The operator of each vessel subject to the pollution regulations is NOT required to keep written records of __________.
Hose information not marked on the hose
Cargoes carried and dates delivered, including destinations
The date and results of the most recent equipment inspection
The name of each person designated as a person in charge
An ocean going ship of 4000 gross tons must be fitted with a standard discharge shore connection for the discharge of oily wastes to a reception facility. The dimensions for the connection are specified in the Pollution Prevention Regulations under Part _
151
153
154
155
An ocean going ship of 4000 gross tons must be fitted with a standard discharge shore connection for the discharge of oily wastes to a reception facility. The dimensions for the connection are specified in the Pollution Prevention Regulations under Part _
154
153
155
151
An ocean going ship of over 400 gross tons must be fitted with a standard discharge shore connection. What size bolt circle diameter is required for this shore connection to transfer oily ballast to a shore side reception facility
183
125
215
250
Pollution Prevention Regulations state that no person may transfer oil to or from a vessel unless _____________.
A sample has been taken from the oil being received
Hoses are supported so that couplings have no strain on them
Each part of the transfer system is blown through with air
An oil containment boom is available for immediate use
According to regulations, when loading, or discharging oil in bulk at a dock, which of the following signals must be displayed?
A signal is not required for discharging oil, only gasoline
A yellow flag (day), red light (night)
A green flag (day), green light (night)
A red flag (day), red light (night)
A shipboard oil pollution emergency plan is required of ______________.
All vessels, regardless of size and commercial application
Any barge or other ship which is constructed or operated in such a manner that no oil in any form can be carried aboard
An oil tanker of 400 gross tons and above, or other ships of 10 gross tons and abov
An oil tanker of 150 gross tons or above, or other ship of 400 gross tons or above
Shipboard oil pollution emergency plans must be reviewed ___________..
Annually by the owner and submit a letter to the Coast Guard within one month of the anniversary date of the plan approval
Only once every five years and a letter submitted six months prior to expiration
Annually by the owner and a letter sumitted six months prior to expiration
And the entire plan resubmitted for approval once every five years, six months prior to expiration
Coast Guard Regulations require the emergency bilge system to _____.
Have a cross connection to the ballast system
Be independent of the main bilge system
Be a part of the independent bilge system
Have an independent priming pump
Coast Guard regulations require a shipboard oil pollution emergency plan to be reviewed
Biennially only
Annually only
Quad‐annually only
Only one every five years
The term arrival ballast refers to ___________.
Any form of sea water ballast
Dirty ballast
Clean ballast
Brackish water ballast
Water ballast placed in a tank that has been crude oil washed, but not water rinsed, shall be regarded as ________.
Dirty ballast
Clean ballast
Crude oil
Segregated ballast
Regulations, state that ocean going ships of 400 gross tons and above must be fitted with a standard discharge shore connection for the discharge of oily waste from machinery space bilges to reception facilities. The flange of this discharge connection mu
10 mm in thickness
Designed to accept pipes up to a maximum internal diameter of 100mm
Suitable for a service pressure of 6 kg/cm2
Slotted to receive eight bolts and 20 mm in diameter
In an oil pumping operation where pumping connections are made up of flanged hoses the weakest link is the _________.
Bolt hole
Stud
Flange
Hose
The term segregated ballast is defined in the Pollution Prevention Regulations as ballast water introduced into a/an ____________.
Isolated tank for analysis because of its noxious properties
Water separator for segregation
Tank that is completely separated from the cargo oil and fuel oil systems
Fuel settling tank for segregation from lighter fluids
Pollution Prevention Regulations require that on the completion of oil transfer operations all _____________.
Hoses shall be blown down with air
Persons on duty during oil transfer shall be accounted for
Soundings shall be entered in the oil record book
Valves used during transfer shall be closed
Remote control for stopping machinery driving fuel oil service pumps is required. These controls shall be _______.
Provided with a locked cover
Protected against accidental operation
Located at the control platform
Essible to authorized personnel only
According to Regulations (46 CFR), no vessel can come alongside or remain alongside a tank vessel while it is loading A, B, or C grade cargo without having the permission of the ____________.
USCG captain of the port
Officer‐in‐charge of the vessel which is loading
Terminal manager
Tank ship owner
To avoid oil from discharge into the sea when ballasting _______________.
Start the cargo p/p then close sea suction valve
Start cargo p/p then open sea discharge valve
Start cargo p/p then open sea strainer valve
Start the cargo p/p then open sea suction valve
Which of the following liquids can ordinarily be discharge overboard without being processed through an oily water separator?
Cargo pumproom bilges
Engine room bilges
Cargo tank ballast
Segregated ballast
No person may transfer oil to or from a vessel unless the person in charge
Is in the immediate vicinity and immediately available to the oil transfer personnel
Has in his or her possession a copy of the vessels Oil Record Book
Has notified the captain of the port at least 24 hours before beginning each oil transfer operation
Has in his or her possession a valid Certificate of Inspection or Tank Vessel Examination Letter
When completing the ballasting operation of a contaminated tank, which of the following problems must be guarded against?
Loss of pump suction
Back flow of contaminated water
Insufficient pump pressure when topping of
Motor overload due to high discharge head
To prevent oil from escaping into the sea when ballasting through the cargo piping system, you should FIRST _________.
Open sea suction valves, then start the cargo pump
Open block valves, then start the cargo pump
Open sluice valves, then start the cargo pump
Start the cargo pump, then open sea suction
During topping off of bunker tanks, the loading rate must be personally supervised by the ____________.
Person‐in‐charge
Terminal operator
Master
Chief engineer
The minimum number of bolts necessary for a standard ANSI oil transfer hose temporary flange coupling (eight bolt hole flange) is ____________________.
Six bolts
Two bolts
Four bolts
Eight bolts
According to Pollution Prevention Regulations, when may a person serve as the person‐in‐charge of both a vessel and a facility during oil transfer operations?
When licensed as a certified refueling officer.
Whenever the vessel is short of manpower.
When authorized by the Captain of the Port.
Whenever the facility is unmanned.
Which significant combustion elements of fuel oil is a major source of air pollution/
Hydrogen
Sulphur
Carbon
Nitrogen
Which list is not required to be provided as part of the appendices of the Shipboard Oil Pollution Emergency Plan?
List of agencies or officials in regularly visited ports.
Incident reports
Must be notified.
A list of personnel duty assignments.
Why is it important for fuel oil tank not to be topped off when loading cold oil?
The change in its specific volume when heated may cause an overflo
Air pockets may cause the fuel oil to bubble out of the ullage hole
The fuelling valve may become stuck closed and cause the fuel oil to spill before the valve can be opened
Increased viscosity of the product needs higher loading pressure which increases the chance of spill
The Shipboard Oil Pollution Emergency Plan must include __________.
A one‐line schematic of the plan to be implemented
An explanation and purpose of the plan
The operating instructions for any and all oily‐water separators installed aboard the vessel
All information ordinarily provided in the Oil Record Book
Before a vessel can pump oily water within a Special Area, it has to comply with the following conditions except_________.
It must be more than 12 miles from the nearest coast
Have an oily water separating system in operation
That the filter system have an automatic cut‐off when the wastes are found to exceed 15 ppm of oily residue
Be underway
If you observe any situation which presents a safety or pollution hazard during fuel transfer operations which action should you take first?.
Notify the person in charge of the shore facility.
Close the valves at the manifold.
Shut down the operation.
Sound the general alarm.
To whom is the first report rendered in the oil pollution contingency plan of the vessel?
Coast guard
Ship's agent
Port authorities
Ship's owner
a tanker ship, sanitary inspections of the crew's quarters are the responsibility of the __________.
Master and union delegate
Master and Chief Engineer
Master and Second Mate
Master and Chief Mate
Among other restrictions, an oil tanker may not discharge an oily mixture into the sea from a cargo tank, slop tank, or cargo pump room bilge unless the vessel is_________ .
Discharging at an instantaneous rate of oil content not exceeding 30 liters per nautical mile
At anchor or stopped
More than 12 nautical miles from the nearest land
Is within "Special Areas" defined in Regulation 1 (10) of Annex I to MARPOL 73/78
Under the Pollution Regulations, when you dump garbage in to the sea you must __________.
Make an entry in the Official Logbook
No action is required if you are more than 25 miles from land and no plastic materials are dumped
Notify the U.S. Coast Guard
Keep a record for two year
When amendments are made to the Shipboard Oil Pollution Emergency Plan, the revisions must be submitted to the administration __________.
One month before the anniversary date of the plan
And cannot be implemented without approval
And can be implemented without immediate approval as long as final approval is received within six months of submission
Six months before the end of the approval period
Which is a mandatory section of the shipboard Oil Pollution Emergency Plan?
Removal equipment list
Planned exercises
Reporting requirements
List of individuals required to respond
Which is not a mandatory part of the Shipboard Oil Pollution Emergency Plan?
Diagrams
National and local coordination
Steps to control a discharge
Reporting requirements
Pollution regulation requires that each scupper in an enclosed deck area have a __________.
Wooden plug
Mechanical means of closing
Two‐piece soft patch
Soft rubber plug
According to the Coast Guard Pollution Prevention Regulations (33 CFR), what is the minimum number of bolts required in a temporarily connected standard ANSI coupling?
4 bolts
2 bolts
6 bolts
8 bolts
Pollution Prevention Regulations, state that no person may transfer oil to or from a vessel unless _____________.
Oil residue has been drained from all hoses
An oil containment boom is available for immediate use
All parts of the transfer system have been properly lined up
A representative sample has been taken from the oil being received
Ccording to the Pollution Prevention Regulations, the declaration of inspection is the ____________.
Paper issued by the Coast Guard marine inspector which allows you to conduct a transfer operation
Annual report submitted by vessel personnel to the Coast Guard declaring that all transfer equipment has been inspected
Application you must complete and submit to the Coast Guard to have an inspector visit your vessel
Document signed by vessel and shore facility persons‐in‐charge declaring that all transfer requirements have been met
According to the Pollution Prevention Regulations, who makes the final decision of when oil transfer may begin?
Any local Coast Guard representative
The designated person in‐charge
The captain of the port
The senior deck officer present
According to Pollution Prevention Regulations, if a cargo hose shows a small leak in its fabric, you may transfer oil after______________.
The terminal foreman is notified
The hose is replaced
A drip pan is placed under the leak
The hose leak is securely wrapped
According to Pollution Prevention Regulations (33 CFR), the minimum number of bolts permitted in an ANSI standard flange on an oil hose is_______________.
Nine
Six
Four
Three
The standard outside diameter pipelines to enable pipes of reception facilities to be connected with the ships discharge pipelines for residues from machinery bilges should be_________.
215 mm
225 mm
250 mm
235 mm
Plastic material may be discharged overboard from a vessel if it is __________.
3 miles from shore
12 miles from shore
25 miles from shore
Prohibited to throw overboard
One of the requirements for an oil tanker operating with Dedicated Clean Ballast shall be that it is equipped with_________.
An oil content meter
A COW system
Segregated Ballast Tanks and PL
Two separate slop tanks
Why is it important for fuel oil tank not to be topped off when loading cold oil?
Increased viscosity of the product needs higher loading pressure which increases the chance of spill
Air pockets may cause the fuel oil to bubble out of the ullage hole
The fuelling valve may become stuck closed and cause the fuel oil to spill before the valve can be opened
The change in its specific volume when heated may cause an overflow
{"name":"C-10", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"The operator of each vessel subject to the pollution regulations is NOT required to keep written records of __________., An ocean going ship of 4000 gross tons must be fitted with a standard discharge shore connection for the discharge of oily wastes to a reception facility. The dimensions for the connection are specified in the Pollution Prevention Regulations under Part _, An ocean going ship of 4000 gross tons must be fitted with a standard discharge shore connection for the discharge of oily wastes to a reception facility. The dimensions for the connection are specified in the Pollution Prevention Regulations under Part _","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}