In the absence of specific instructions to the contrary in the contract documents, the AISC COSP shall govern.
True
False
According to the COSP, demolition should be a standard part of the steel scope.
True
False
The COSP sets out several options for determining which party is primarily responsible for steel connection design. How many options are given?
1
2
3
4
The fabricator is entitled to payment for stored or re-ordered materials due to schedule delays and/or design changes.
True
False
The shop coat is intended...
As a final finish coat.
As a prime coating to be field painted later.
To fully protect the steel from any atmospheric conditions.
To protect the steel from short term nortmal atmospheric exposure.
Select the minimum requirements for job site conditions:
Firm
Properly Graded
Adequate Space
Poured Full Strength Slab
The steel erector is responsible for grouting the base plates.
True
False
When temporary rail is left in place for other trades to use after we have vacated an area, who is responsible for removing it?
Steel Erector
Cooper On Site PM
GC
Customer/Owner
If we locate AESS requirements in the construction documents, but the category is not specified, what should we do?
Assume a category and price it
Ignore it
Submit an RFI, exclude if no answer
Call the engineer
Structural elements that are sub-assembled in the field prior to erection (such as trusses) are subject to shop tolerances.
True
False
{"name":"AISC Code of Standard Practice Quiz", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"In the absence of specific instructions to the contrary in the contract documents, the AISC COSP shall govern., According to the COSP, demolition should be a standard part of the steel scope., The COSP sets out several options for determining which party is primarily responsible for steel connection design. How many options are given?","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}