05- Scope Management

Which term has the definition of a condition or capability that is required to be present in a product, service, or result to satisfy an agreement or other formally imposed specifications?
Requirement
Deliverable
Feature
Prerequisite
Which process brings objectivity to the acceptance process and increases the probability of final product, service, or result acceptance?
Validate Scope
Control Scope
Manage Quality
Control Quality
Tariq is a recently certified PMP and a recently hired project manager. Tariq has a strong and motivating desire to become accustomed to working with his new team as soon as possible, Tariq's mentor and coach Andrew would like Tariq to create a question of the day for the rest of his project management team to get to know the other team members. Tariq's question of the day is ""what technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?"" What is the correct answer?
Decomposition
Rolling wave planning
Breakdown
Progressive elaboration
What is a component of the project management plan that describes how the scope will be defined, developed, monitored, controlled, and validated?
Scope management plan
Project scope statement
Requirements management plan
Requirements documentation
Helen is an experienced project manager and is coaching and training Sally, who is a recently certified PMP. Every morning they have coffee together in the cafeteria, where they discuss different aspects of project management. This morning Helen quizzes Sally by asking her which PMBOK® Guide process will monitor the status of the project and product scope. What is Sally's best response?
Control Scope
Validate Scope
Monitor and Control Project Work
Direct and Manage Project Work
Glen is a seasoned project manager and a voracious reader of project management topics and best practices. While reading the PMBOK® Guide 6th Edition, Dan discovered an emerging practice concept new concept he had not seen in the PMBOK® Guide 5th Edition. The following statement explain this new concept but has one portion missing. ""As the global environment becomes more complex, organizations are starting to recognize how to use which of the following to their competitive advantage by defining, managing, and controlling requirements?"
Business analysis
Agile methods
Requirements
Hybrid methods
What is the process name that is used for determining, documenting, and managing stakeholder needs and requirements to meet objectives?
Collect Requirements
Plan Scope Management
Define Scope
Create WBS
Which of the following methods would be best to implement for projects with high risk, significant uncertainty, and where the scope of the project is not clearly understood at the beginning of the project but will evolve during the life of the project?
Agile method
Hybrid method
Predictive method
Incremental method
What is the name of the work breakdown structure component that is below the control account and above the work package?
Planning package
Code of accounts
WBS
WBS dictionary
Jason is a key stakeholder on your project. He has just finished an inspection of the completed product component for this project phase, and formally signs off on it. What is the PMBOK® Guide term for this completed product component?
Accepted deliverables
Verified deliverables
Partial deliverables
Approved deliverables
{"name":"05- Scope Management", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Which term has the definition of a condition or capability that is required to be present in a product, service, or result to satisfy an agreement or other formally imposed specifications?, Which process brings objectivity to the acceptance process and increases the probability of final product, service, or result acceptance?, Tariq is a recently certified PMP and a recently hired project manager. Tariq has a strong and motivating desire to become accustomed to working with his new team as soon as possible, Tariq's mentor and coach Andrew would like Tariq to create a question of the day for the rest of his project management team to get to know the other team members. Tariq's question of the day is \"\"what technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?\"\" What is the correct answer?","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}