Construction Scheduling Mastery Quiz

A detailed infographic representation of construction scheduling concepts, including graphs, timelines, and architectural elements related to project management in a modern style.

Construction Scheduling Mastery Quiz

Test your knowledge about construction scheduling practices and guidelines relevant to the DPWH. This quiz includes 10 multiple-choice questions covering topics such as project management, scheduling techniques, and specific Department Orders.

  • Enhance your understanding of construction schedules
  • Challenge your knowledge with 10 diverse questions
  • Track your progress in project planning
10 Questions2 MinutesCreated by BuildingBridge321
Who will prepare the complete set of the Construction Schedules prior to the signing of the Contract?
Bids and Awards Committee
Planning and Design Section/Division
Contractor
Construction Section/Division
According to Annex “A” of the Revised IRR of RA ______, the program of work shall include, among other things, estimates of work, items, quantities and costs and a PERT/CPM network of the project activities.
9184
8194
9148
8149
It is the amount of time a scheduled activity may either be delayed or extended from its early start date without delaying the project finish date.
Dummy
Float
Lag
Lead
It is the Department Order instructing the adoption of the PDM as the project scheduling technique to be utilized in DPWH infrastructure projects.
D.O. no. 137, series of 2016
D.O. no. 137, series of 2015
D.O. no. 133, series of 2015
D.O. no. 133, series of 2016
Which of the following is NOT a use of Construction Schedules in DPWH projects?
Determination of Construction Duration
Decision Making
Monitoring of Accomplishments
Basis for Billings
Complete the Forward Pass. Duration of Activity C is 30. See Figure 3.
15 and 45
20 and 50
35 and 65
50 and 80
Complete the Backward Pass. Duration of F is 20. See Figure 4.
40 and 60
50 and 70
45 and 65
65 and 85
What is the DPWH Standard PDM Node? See Figure 2.
A
B
C
D
Given the S-Curve, what is the reason for the revision? See Figure 1
Time Extension without Variation Order
Variation Order without Time Extension
Suspension and Resumption Order
Variation Order with Time Extension
What is the percent weight distribution in a Normal S-Curve?
20-30-30-20
25-50-25
25-25-25-25
30-40-30
{"name":"Construction Scheduling Mastery Quiz", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Test your knowledge about construction scheduling practices and guidelines relevant to the DPWH. This quiz includes 10 multiple-choice questions covering topics such as project management, scheduling techniques, and specific Department Orders.Enhance your understanding of construction schedulesChallenge your knowledge with 10 diverse questionsTrack your progress in project planning","img":"https:/images/course4.png"}