Work Schedule (Part 1)

Create an illustration depicting a project management scene with construction schedules, S-Curve graphs, and planners discussing over blueprints.

Work Schedule Mastery Quiz

Test your knowledge on construction scheduling techniques and the DPWH standards with our engaging quiz! This quiz consists of 10 thought-provoking questions designed to challenge your understanding of project management.

You'll learn about:

  • The S-Curve and its implications
  • DPWH Standard PDM Nodes
  • Construction Schedules and their uses
10 Questions2 MinutesCreated by SchedulingExpert47
Given the S-Curve, what is the reason for the revision? See Figure 1.
A. Time Extension without Variation Order
B. Variation Order without Time Extension
C. Suspension and Resumption Order
D. Variation Order with Time Extension
What is the DPWH Standard PDM Node? See Figure 2.
A
B
C
D
What is the percent weight distribution in a Normal S-Curve?
A. 20-30-30-20
B. 25-50-25
C. 25-25-25-25
D. 30-40-30
What does the acronym PDM stand for?
A. Precedence Diagram Method
B. Presedence Diagram Method
C. Precedence Diagramming Method
D. Presedence Diagramming Method
Who will prepare the complete set of the Construction Schedules prior to the signing of the Contract?
A. Bids and Awards Committee
B. Planning and Design/Division
C. Contractor
D. Construction Section/Division
According to Annex “A” of the Revised IRR of RA ______, the program of work shall include, among other things, estimates of work, items, quantities and costs and a PERT/CPM network of the project activities.
A. 8194
B. 9148
C. 9184
D. 8149
It is the amount of time a scheduled activity may either be delayed or extended from its early start date without delaying the project finish date.
A. Dummy
B. Float
C. Lag
D. Lead
It is the Department Order instructing the adoption of the PDM as the project scheduling technique to be utilized in DPWH infrastructure projects.
A. D.O. no. 137, series of 2016
B. D.O. no. 137, series of 2015
C. D.O. no. 133, series of 2015
D. D.O. no. 133, series of 2016
Which of the following is NOT a use of Construction Schedules in DPWH projects?
A. Determination of Construction Duration
B. Decision Making
C. Monitoring of Accomplishments
D. Basis for Billings
Complete the Forward Pass. Duration of Activity C is 30. See Figure 3.
A. 15 and 45
B. 20 and 50
C. 35 and 65
D. 50 and 80
{"name":"Work Schedule (Part 1)", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Test your knowledge on construction scheduling techniques and the DPWH standards with our engaging quiz! This quiz consists of 10 thought-provoking questions designed to challenge your understanding of project management.You'll learn about:The S-Curve and its implicationsDPWH Standard PDM NodesConstruction Schedules and their uses","img":"https:/images/course5.png"}