1- Project Environments

Which of the following is considered an enterprise environmental factor (EEF)?
Benchmarking results
Product and project life cycles
Specific communication technology available
Risk register
Which of the following is not considered a valid type of PMO?
Operational PMO
Directive PMO
Supportive PMO
Controlling PMO
Governance is the framework within which authority is exercised in organizations. Which of the following is a true statement concerning what governance influences on a project?
How risk is monitored and assessed.
How the PMO is structured and operates.
How to perform vendor selection.
How to perform project termination.
Which of the following statements is true regarding the projects supported or administered by the Project Management Office (PMO)?
The projects may not be related other than by being managed together.
The projects must all be related to each other.
The projects must be in the same program.
The projects must be in the same portfolio.
Which of the following is not considered an organizational process asset (OPA)?
Existing human resources expertise.
Resource availability control and assignment management.
Time reporting.
Preapproved supplier lists.
A project management office (PMO) may have the authority to act as an integral stakeholder and a key decision maker throughout the life of the each project. Which one of the following cannot ever be done for a project by a PMO?
Never terminate a project.
Lead knowledge transfer sessions.
Make recommendations.
Take other action as required.
Who is responsible for examining optimization trade-offs between a system and its components on a project?
The project manager
Senior management
The project sponsor
The functional manager
In order to operate effectively and efficiently, the project manager needs to clearly understand where responsibility, accountability, and authority reside within the performing organization. Where can the project manager obtain this important information?
Organizational system
Organizational process assets
Enterprise environmental factors
Management elements
Organizational structure types can have an influence on project execution. Which of the following is not considered an organizational structure type?
Complex
Virtual
Hybrid
Multi-divisional
For organizational structure types, determination of the appropriate organizational structure type is a result of the study of tradeoffs between two key variables. Which two key variables are correct?
The organizational structure types available for use and how to optimize them for a given organization.
There are no two key variables.
There is a one-size-fits-all structure for any given organizational structure.
The authority of the functional manager and the authority of the project manager.
{"name":"1- Project Environments", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Which of the following is considered an enterprise environmental factor (EEF)?, Which of the following is not considered a valid type of PMO?, Governance is the framework within which authority is exercised in organizations. Which of the following is a true statement concerning what governance influences on a project?","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}
Powered by: Quiz Maker