Exit Exam Reviewer
Civil Engineering Exit Exam Reviewer
Test your knowledge with our comprehensive quiz designed for aspiring civil engineers. This quiz covers a variety of topics relevant to civil engineering principles and practices.
With questions spanning structural analysis, material properties, and project management, you can:
- Enhance your understanding of civil engineering
- Prepare for exams and certification
- Challenge your knowledge with practical scenarios
1. In order to be recycled, concrete cannot contain..
Water
Aggregate
None of the above
Sand
A soil has a specific gravity of 2.68 and a void ratio of 0.73 if the degree of saturation is 92%. Compute the dry density of the soil in g/cc.
1.97
1.74
2.03
1.55
A plain round bar made out of steel weighs 0.5 kg with dimensions of 15 mm in diameter and 1.5m in length. Calculate for its density in g/cc.
1.887 g/cc
2.280 g/cc
2.281g/cc
1.886 g/cc
What is the effect of staggered holes in steel tension members?
INCREASE TENSILE STRENGTH
REDUCE TENSILE STRENGTH
None of the Above
DOES NOT AFFECT THE TENSILE STRENGTH OF MEMBER
It is a measure of the size of the particle of cement
Soundness
Normal consistency
Time setting
Fineness
The steel tensile strain limit ofr a tension- controlled failure is
0.009
0.007
0.005
0.003
It is a government policy covering technical requirements in constructing or renovating building and structures in the Philippines to secure the life, health, property and welfare of the Filipinos
National structural code
Presidential decree #1096
Building permit requirement
Architectural and structural plans
Concrete compressive strain is expected to be at____ when the concrete is on the verge of crushing as per NSCP
0.006
0.008
0.003
0.009
The branch of engineering that deals with improvement of traffic performance, traffic studies and traffic network is called _____
Highway engineering
Traffic management
Railway engineering
Traffic engineering
A floor joist 50mm x 200mm has a span of 5m. If it carries a total floor load of 5kPa. Determine the spacing if the joist in mm to develop a bending stress of 8 MPa.
270mm
120mm
150mm
170mm
If civil engineers inform the client via document about a certain change involving site implementation then civil engineers can already implement the change with or without the approval of client.
True
False
An open channel to be made of concrete is to be designed to carry 5 m^3/s at a slope of 0.000655. Find the most efficient cross section for (a) semicircular section (solve for diameter the in m)
1.847 m
1.645 m
1.457 m
1.954 m
Which of the following does not belong to the group?
Nuclear Method
Sand-Cone Method
Fall Cone Method
Rubber Balloon Method
Metropolitan Manila has a road network following which type of road pattern?
Radial or Circular Pattern
Rectangular Pattern
Hexagonal Pattern
Radial or Star Pattern
In Project Management, it refers the sequence of project network activities which add up to the longest overall duration. This determines the shortest time possible to complete the project.
Risk
Scheduling
Critical Path
None of the above
It is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives such as scope, schedule, cost, and quality.
All of the above
Risk
Critical Path
Scheduling
Reservoir A has an elevation of 300m circular pipe is connected to it with diameter of 300mm and length of 200m, while Reservoir B is at elevation 200m with circular pipe connected to it diameter 250m and Reservoir C elevation 150 with a circular pipe attached to it, diameter is 600mm and length is 450m. All pipes meet at a junction. Determine the flow rate in Pipe A in m3/s. Use f=0.02.
0.994 m3/s
0.224 m3/s
0.745 m3/s
0.992 m3/s
Locational clearance requirements in acquiring building permit are the following except:
Architectural Plan
Site Development Plan
Foundation Plan
Lot Plan
They are flat horizontal panels that support the floor.
Beams
Columns
Footings
Slabs
If super-elevation is not provided on a horizontal curve of a highway, then on which portion of the road, are pot holes likely to develop?
Center of road
Inner edge of road
Shoulder of road
Outer edge of road
The maximum super elevation to be provided on a road curve is 1 in 15. If the rate of change of super elevation is specified as 1 in 120 and the road width is 10m, then the minimum length of the transition curve on either end will be:
80 m
30 m
180 m
125 m
The resistance factor for tension in structural steel in gross section yielding is
90%
65%
75%
85%
A surveying student walked along a given line that was known to be 200.0 ft long to determine her average unit pace. She paced the line four times, recording 78, 76.5,77 and 76 pace, respectively in her field book. If the surveyor then counted an average of 123.5 paces while pacing off a line of unknown distance, what is the distance?
325.70 ft
321.30 ft
320.25 ft
328.30 ft
It is the minimum distance required to stop a vehicle before it reaches a stationary object
Decision Sight Distance
Stopping sight distance
Passing sight distance
Intersection sight distance
A curving roadway has a design speed of 80 km/hr. At one horizontal curve, the superelevation has been set at 6% and the angle of side friction is found to be 6". Determine the impact factor.
0.19
0.17
0.20
0.16
In general, it is the densification of soil by removal of air, which requires mechanical energy
Compaction
None of the above
Consolidation
Compression
A summit curve is formed at the intersection of a 3% up gradient and 5% down gradient. To provide a sopping sight distance of 128 m, the length of summit curve needed will be:
298mm
322mm
271mm
340mm
Calculate the steel ratio that will produce a tension-controlled failure if compressive strength f’c=28 MPa and steel yield strength fy=350 MPa.
0.03258
0.02167
0.02617
0.04567
Reservoir A has an elevation of 300m circular pipe is connected to it with diameter of 300mm and length of 200m, while Reservoir B is at elevation 200m with circular pipe connected to it diameter 250m and Reservoir C elevation 150 with a circular pipe attached to it, diameter is 600mm and length is 450m. All pipes meet at a junction. Determine the flow rate in Pipe A in m3/s. Use f=0.02.
0.994 m3/s
0.224 m3/s
0.745 m3/s
0.992 m3/s
Which of the following is always TRUE about Big Data?
I. Due to its size or structure, Big Data cannot be efficiently analyzed using only traditional databases or methods
II. Although the variety of Big Data tends to attract the most attention, generally the volume and velocity of the data provide a more apt definition of Big Data.
I only
II only
Both I and II
Neither I nor II
Which of the following is try about the current analytical architecture?
I Data sources are first loaded into the data warehouse where data needs to be well understood, structure, and normalize with the appropriate data type definition. This kind of centralizations enables security, backup, and failover of highly critical data.
II Once in the data warehouse, data is read by additional applications across the enterprise for BI and reporting purposes. These are high-priority operational processes getting critical data feeds from the data warehouse and repositories.
I only
II only
Both I and II
Neither I nor II
Which of the following are problems encountered in traditional data architecture?
High-value data is hard to reach and leverage, and predictive analytics and data mining activities are last in line for data
Data scientists are limited to performing in-memory analytics which will restrict the size of the datasets they can use
Data science projects will remain isolated and ad hoc, rather than centrally managed
All of the above
Among the business drivers that push businesses to become more analytical and data drive, this one involves customer churn, fraud and default.
Optimize Business operation
Identify Business risk
Predict new business opportunities
Comply with regulatory requirements
This are centralized data containers in a purpose-built space that supports business intelligence and reporting but restricts robust analyses.
Data marts
Data warehouses
Analytic sandbox
None of the above
Which of these attributed stand out as defining Big Data characteristics?
Huge volume of data
Complexity of data types and structures
Speed and new data creation and growth
All of the above
Metropolitan Manila has a road network following which type of road pattern?
Radial or Circular Pattern
Rectangular Pattern
Hexagonal Pattern
Radial or Star Pattern
Civil engineers can act independently as long as it is written in the contract
True
False
These members are generally vertical and resist axial compressive loads
Slabs
Beams
Columns
Footings
This type of data has no inherent structure, which may include text documents, PDFs, images and video. (Quasi-structures Data, Unstructured Data, Semi-structured Data, Structured Data)
Quasi-structures Data
Unstructured Data
Semi-Structured Data
Structured Data
Which of the following TRUE about the differences of Business Intelligence (BI) and Data Science?
I. Where Data Science problems tend to require highly structured data organized in
rows and columns for accurate reporting. BI projects tend to use many types of
data sources, including large or unconventional datasets.
II. Data Science tends to be more exploratory in nature and may use scenario
optimization to deal with more open-ended questions.
rows and columns for accurate reporting. BI projects tend to use many types of
data sources, including large or unconventional datasets.
II. Data Science tends to be more exploratory in nature and may use scenario
optimization to deal with more open-ended questions.
I only
II only
both I and II
neither I nor II
Which of these attributes stand out as defining Big Data characteristics?
Huge volume of data
Complexity of data types and structures,
Speed of new data creation and growth
All of the above
{"name":"Exit Exam Reviewer", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Test your knowledge with our comprehensive quiz designed for aspiring civil engineers. This quiz covers a variety of topics relevant to civil engineering principles and practices.With questions spanning structural analysis, material properties, and project management, you can:Enhance your understanding of civil engineeringPrepare for exams and certificationChallenge your knowledge with practical scenarios","img":"https:/images/course8.png"}
More Quizzes
Exit Exam
3015164
EXIT EXAM
301530
Compre Set. 85
100500
Provisional Field Engineers Reviewer (A)
10050131
Civil Engineering Random Quiz
5230
Item 200 and 201
10522
Transportation Engineering
1168
Item 311
10527
BUILDING CONSTRUCTION METHODS
8542206
Compre Reviewer Part 1
10050240
Item 505 - Riprap and Grouted Riprap
10520
Unsaturated Soil Mechanics Quiz
67340