Mastering Project Management with Gantt Charts

Test your knowledge on project management concepts, specifically focusing on Gantt charts and their features! This quiz consists of 10 intriguing multiple-choice questions that will challenge your understanding and application of essential project management principles.

Topics covered include:

  • Understanding Gantt chart components
  • Dependencies and their management
  • Key project management terminology
10 Questions2 MinutesCreated by PlanningPro27
The modern Gantt chart is formed of
Textual Outline
Calendar Graph
Textual Outline+Calendar Graph
None
In The modern Gantt chart Deliverable is set as diamonds
T
F
it is possible to “undo” soft dependencies
T
F
Lag time = delay introduced by the dependency is negative
T
F
Not all activities are equally important or critical in a plan
T
F
AON is
Activity on Network
Action on Node
Activity on Node
Action on Need
Slack an activity has before delaying whole project
Total Slack
Free Slack
Delayed Slack
Early Slack
What determines the earliest start and end dates of each activity in the plan
forward pass
Backward pass
Critical path
Slack path
Resource usage is computed by summing the amount of work required for any given period
T
F
Overallocation is a situation in which a resource is used below his/her/its maximum capability
T
F
{"name":"LEC8", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Test your knowledge on project management concepts, specifically focusing on Gantt charts and their features! This quiz consists of 10 intriguing multiple-choice questions that will challenge your understanding and application of essential project management principles.Topics covered include:Understanding Gantt chart componentsDependencies and their managementKey project management terminology","img":"https:/images/course6.png"}